Please remind Reviewers comments when developing future activities. WP8 - Project Management. Contractual obligations following the 2 nd Annual Review fulfilled Deliverable D5 – F-MAN Architecture (NTUA) Deliverable D6 – Description of the F-MAN tools (SCIRO)

palmer
Télécharger la présentation

WP8 - Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Please remind Reviewers comments when developing future activities WP8 - Project Management • Contractual obligations following the 2nd Annual Review fulfilled • Deliverable D5 – F-MAN Architecture (NTUA) • Deliverable D6 – Description of the F-MAN tools (SCIRO) • Deliverable D8 – Tracking kernel (SCIRO) • Deliverable D12 – Evaluation Plan (UGDIE) Revised and submitted on December 12th 2003

  2. 3rd Amendment in progress WP8 - Project Management • TECNO withdrawal process completed • Budget transfer request submitted • Time extension request submitted • Three more months to complete the project

  3. WP8 - Project Management • 2nd Cost Statement process completed • Documentation submitted on November 11th 2003 • Payment expected in March-April 2004 • Effort  actual vs. planned • TECNO available man-hours redistributed • Current figures compliant with the budget • 9th QMR (October – December 2003) completed

  4. IVU – WP5 New budget 1710 h Original 1400 h + 310 h from TECNO SCIRO – WP3 New budget 1482 h Original 1350 h + 132 h from TECNO SCIRO – WP5 New budget 1009 h Original 810 h + 199 h from TECNO PI – WP5 New budget 1480 h Original 1200 h + 280 h from TECNO WP8 - Project Management

  5. Budget transfer among different cost figures is allowed through a request to the EC WP8 - Project Management • We will have to prepare 3 more QMRs • January – March 2004 • April – June 2004 • July – September 2004 • Please plan carefully the remaining man-hours available and make step by step a forecast of the costs you will claim by the end of the project in order to avoid any over budget

  6. Project completion – Milestone M5 postponed on 30 September 2004 Deliverable D13 – Deliverable D15 – Deliverable D16 postponed on 30 September 2004 WP4 completion – Milestone M4 – Deliverable D10 postponed on 30 June 2004 WP5 completion – Deliverable D11.2 postponed on 31 July 2004 WP8 - Project deadlines

  7. Conclusions Dear friends, I hope you have not found too boring my presentation. All my best for a fruitful meeting. Sorry, but I have to leave. My physiotherapist is just waiting for a session. Really a hard job. Ciao. Stefano