170 likes | 246 Vues
Stay updated on the MC Beamline Project's scope, costs, schedule, and status, with key insights on organization, site plan, and potential challenges. Take necessary actions with strategic cost curves for efficient management.
E N D
MC Beamline Tom lackowski L1 Manager
Agenda • Project Charter • Scope • Schedule Cost • Status and Issues T. Lackowski - MC Beamline
Project Organization T. Lackowski - MC Beamline
Site Plan T. Lackowski - MC Beamline
Scope • Main Injector type enclosure • 10 feet wide x 8 feet high (typical except near MC-1 where higher ceiling will be required. • Painted walls and ceiling, sealed floor. Floor to have 3” cover over rebar to enable stand anchorage. • Channel inserts walls and ceiling @ 8’ o/c. (no inserts 5’ from floor on aisle side) • Shielding • 16 feet of earth/concrete for M-4 beamline. (w/ beamline 4’ from clg.) • 6 to 9 feet for g-2 beamline. Shielding needed within enclosure between MC-1 building and M-4 / Delivery Ring. • Access for magnets is provided directly from Ring enclosure; lift provided for magnet installation. Shielded hatch provided for magnet installation / replacement. T. Lackowski - MC Beamline
Typical Cross Section T. Lackowski - MC Beamline
Scope • HVAC & Process Water • A concept exits that integrates the requirements for beamline and Mu2e. G-2 is isolated from beamline. • LCW provided by g-2 and Mu2e projects. • Electrical • 500 MCM ground along beamlines. • Quad 120V & duplex 208V utility outlets at 60’ • 480V welding outlets at 400’ • Three 18” cable trays provided (one tray will contain line type heat detection) • Lighting 20 FC; UPS in MC-1 Building for emergency lighting. T. Lackowski - MC Beamline
Cost by Division T. Lackowski - MC Beamline
P6 Schedule T. Lackowski - MC Beamline
P6 T. Lackowski - MC Beamline
P6 T. Lackowski - MC Beamline
GPP Milestone Schedule T. Lackowski - MC Beamline
Current Muon Campus Fiscal Cost and Proposed Schedule T. Lackowski - MC Beamline
Preliminary Costs T. Lackowski - MC Beamline
Cost Curve T. Lackowski - MC Beamline
Status and Issues • Beamline lattice not complete past bend • Holding up Project Plan completion • Depending on geometry of final layout there may be some exiting issues that must be resolved (Additional stair @~$175K) • Project plan text 80% complete. • Budget exceeded ($9.7M vs. $9.2 M), close to $10mil cap. Additional funding in FY14 most beneficial. • Indirect costs have increased and recent history indicates that there is a negative risk of additional increases. • There is little in the way of deduct scope contingency that would not need to be transferred to one of the other projects. T. Lackowski - MC Beamline
Current GPP Program T. Lackowski - MC Beamline