1 / 11

Cost Allocation for IROL Critical Generator CIP Costs

The ISO proposes a new tariff mechanism to allocate the costs of CIP equipment and procedures for IROL-critical generators to electric consumers through charges. This article discusses alternative cost allocation options and the need for transparency in billing.

pitchford
Télécharger la présentation

Cost Allocation for IROL Critical Generator CIP Costs

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cost Allocation for IROL Critical Generator CIP Costs Transmission Committee – March 27, 2019

  2. Background • The ISO plans to designate certain generators as Interconnection Reliability Operating Limits (IROL) “Critical” resources. • This designation may require these resources to add incremental CIP equipment and/or procedures. • The ISO says the cost of this incremental equipment and/or procedures cannot be competitively offered into the energy and capacity markets. • The ISO is proposing a new tariff mechanism that would allow “IROL-critical” generators to seek cost recovery for expenditures approved by FERC. • The ISO’s proposal would allocate these costs to electric consumers through charges born by Regional Network Load (i.e. transmission customers)

  3. Considerations for Cost Recovery • For most businesses, compliance with new regulations is a cost of doing business • Because only some generators are designated as IROL-critical and market-base cost recovery for these expenses, there may some justification for cost-based recovery. • Assuming that CIP costs for IROL critical generators are appropriately eligible for cost-based recovery, recovering these costs through transmission charges is inappropriate. • Transmission charges should primarily reflect the costs of building, operating, maintaining and ensuring the reliability of the transmission system. • Other rate mechanisms should be used to recover the costs of generation equipment or generator expenses.

  4. Alternative Cost Allocation Options • Cost allocation options exist other than Network Load. • Real-Time Load Obligation (RTLO), used for: • Winter fuel reliability programs and fuel security cost-of-service agreements (i.e. Mystic contracts) • Generator performance audit payments • Capacity Load Obligation • Primary mechanism for recovery of generator costs not covered by energy market (i.e. “missing money”) • Real-Time Non-Coincident Peak Load Obligations • Used for ISO Schedule 3 Reliability Administration Service (RAS) to provide other reliability and informational services. • Capacity Load Obligation or Real-Time Non-Coincident Peak Load Obligation are the most appropriate allocator for CIP costs for IROL critical generators • No matter the allocator, the ISO should create a separate billing item to facilitate transparency of these costs

  5. Costs Allocated to Regional Network Load NEW • Infrastructure • Post 1996 Infrastructure • Pre 1997 Infrastructure • Reliability • FCM PDFR Pro-ration Denied for Reliabiliity) • FCM RFR (Retained for Reliability) • High Voltage Control • System Restoration • Voltage Support • Administrative • ISO Dispatch & Control • NESCOE Budget • PTO Dispatch & Control

  6. Typical MA Eversource Residential Bill NEW

  7. Typical NH Eversource Residential Bill NEW

  8. Typical CT Eversource Residential Bill NEW

  9. ISO Self Funding Tariff – Schedule 3 NEW • Reliability Administration Service (Schedule 3) • The ISO provides Reliability Administration Service to administer the Reliability Markets, including the Forward Capacity Market, in accordance with Market Rule 1 and to provide other reliability and informational services. These services are of a type not directly related to the services provided under Schedules 1 and 2, and are expenses of operating the New England Control Area generally, rather than expenses attributable to serving a particular Customer.

  10. ISO Self Funding Tariff – Schedule 3 (cont) NEW • Examples of functions performed: • generation and demand dispatch associated with Reliability Markets; • Reliability Markets accounting; • billing preparation; • generation emissions analysis; • risk profile updates; • triennial review of resource adequacy; • studies and qualification of resources under FCM; • preparation of regional reports and load forecasts and profiles (Capacity, Energy, • Load and Transmission (“CELT”) Reports; reports to the Energy Information • Administration of the United States Department of Energy; reports to NERC; • Regional System Plan); • support of power supply, environmental, and market reliability planning activities; • market power monitoring, mitigation, and assessment for the Reliability Markets; and • formulation of additional market rules and proposals to modify existing rules.

  11. ISO Self Funding Tariff – Schedule 3 (cont) NEW • Schedule 3 allocates internal load activity based on Real-Time NCP [Non-Coincident Peak] Load Obligation. For Exports other than Coordinated External Transactions, Schedule 3 assesses a volumetric (per MWh) charge. Specifically, the ISO divides the Schedule 3 Revenue Requirement by the real-time load obligation forecasted for the upcoming year in the most recent CELT Report to yield the unitized rate per kW-month. The remaining revenue requirement for Schedule 3 (i.e., net of that allocated to Exports) is then divided by the total Real-Time NCP Load Obligation forecast to yield the unitized rate per kW-month.

More Related