1 / 17

Consolidation activities for TE-CRG

12 th September 2013 Accelerator Consolidation Workshop. Consolidation activities for TE-CRG. L. Tavian, TE-CRG. Content. Status of the present approved consolidation program Additional consolidation proposals for: LHC machine AD North Area (NA) (Test areas including HIE- Isolde )

Télécharger la présentation

Consolidation activities for TE-CRG

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 12th September 2013 Accelerator Consolidation Workshop Consolidation activities for TE-CRG L. Tavian, TE-CRG

  2. Content • Status of the present approved consolidation program • Additional consolidation proposals for: • LHC machine • AD • North Area (NA) • (Test areas including HIE-Isolde) • (General cryogenic services)

  3. Status of present consolidation program To be reconsidered w/r to the probability of massive magnet quenches (> half sector) Cancelled (CSAP, LSC, LMC) (Saving of 150 kCHF) New CtC estimate: 225 kCHF (saving of 180 kCHF) + on the LHC detector side, the consolidation of compressor stations: Hot spares for a MTTR < 1 day ! New CtC estimate: 510 kCHF (Extra cost: 50 kCHF in 2013)

  4. Additional proposals for LHC (I) • Continuation of the compressor station consolidation (Chamonix’2012 proposal): • Present situation: • Critical spare available to guarantee a MTTRestore of about 1 week in case of compressor failures at Point 18 and P2. • Proposal: • MTTR of 1 day possible by adding new compressor skids (6 skids: 3 MCHF + EN-EL, EN-ICE, EN-HE support) • Stock availability > 90-95 % by increasing the spare number (4 new spares: 1.2 MCHF)

  5. Additional proposals for LHC (II) • IT cryogenics: • Identified as HW limitation before HL-LHC • Present limitation following 2005-2006 consolidation: Lmax < 1.75 Lnom (considered acceptable at the time) • New consolidation to be studied in collaboration with the equipment owner (TE-MSC) for a consolidation work during the LS2  could be an expensive consolidation. (+ EN-MME, EN-HE support)

  6. Additional proposals for LHC (III) • Consolidation of the LHe storage during LS • During LS1, about 90 t of helium (~2/3 of the LHC inventory) have been send back to the market via “virtual” storage contracts with gas vendors ~ 0.7 MCHF/LS • This helium has to come back at CERN in 2014: return rate compatible with the LS1 schedule  but could be a limiting factor if higher rates are required for future LS. • The possibility to keep a large fraction (~60 tons) of the 90 tons has to be studied: • A small second-hand TCF20 liquefier is under procurement to consolidate 30 t of LHe to be operational for the LS2 (100 kCHFrequired for installation (EN-EL, EN-HE support) • Another liquefier is required to consolidate an additional inventory of 30 t (1.2 MCHF + EN-EL, EN-HE support)

  7. Additional proposals for LHC (IV) • Electricity & instrumentation consolidation • Deported Siemens electronics for control valves in the tunnel: only 1 spare crate available for 150 operating units (10 year old) proposal to increase the spare to ~10 % (300 kCHF).

  8. Additional proposals for AD • AD new cryogenic distribution & recovery infrastructure: • Present situation: • Heavy logistics: up to ~20 dewars (500 l) per week • Clients not familiar nor trained with helium transfer (1 recent accident during summer). Safety (handling and cryogenics) is the concern. • In addition, 20 % of the delivered helium is lost (generally 10 %)  200 kCHF of extra losses per year • Proposal: • Add a new cryogenic distribution and recovery infrastructure  800 kCHF + EN-HE support

  9. Additional proposals for NA (I) • NA62 • Very old LN2 transfer line without redundancy  loss of Krypton inventory (10 MCHF). • Proposal: add a second transfer line and use the old one as redundancy  50 kCHF

  10. Additional proposals for NA (II) • Unicos Controls migration • Controls of cryogenic infrastructure is based on obsolete hardware (ABB) and SCADA (PCvue, ABB): • ATLAS H8 & CMS RD5 • NA62 cool-down & warm-up unit • (SM18 compressor station, SM18 magnet test station) • (B163 and cryolab pumping unit) • (CAST) • No CERN support: Hotline with ABB (10 kCHF per year) and old spare are existing  up to 1 to 2 weeks of downtime in case of major problems. • 650 kCHFneeded for the migration to the UNICOS/PVSS controls system (50 to 150 kCHF per infrastructure)

  11. Additional proposals for test areas (I) • SM18 infrastructure: • Problem with impurities: downtime of 1 week per year for cold box cleaning. New full flow purifier  1 MCHF • Compressor station consolidation: • 2 critical compressors (Stal S93 & S73)  3 to 6 months of downtime • S93 machine recently available in the present LHC spare • S73 machine available following the ATLAS consolidation (but ATLAS property ?)  common ATLAS/SM18 spare with ATLAS priority in case of a low-probable dual need or new spare procurement (0.3 MCHF)

  12. Additional proposals for test areas (II) • HIE Isolde compressor station: • HIE Isolde will reuse in 2014 the ex-ALEPH refrigerator. • No spare are existing for the two cycle compressors (Aerzen VMY236 and VMY436) i.e. 3 to 9 months of downtime in case of major failure. Cannibalization of the CAST refrigerator (ex-DELPHI plant identical) •  or procurement of two new spares (valid for HIE Isolde and CAST) : 0.4 MCHF  MTTRestore of 1 week.

  13. Additional proposals for general cryogenic services (I) • LN2 storage for CERN infrastructure: • Present situation: 3 x 50000 l (NA, Central liquefier and SM18) rented 20 kCHF each per year, for more than 10 years, i.e. more 600 kCHF already spent. • Cost of a storage vessel: 200 kCHF • Proposal: Purchase 3 units (600 kCHF + EN-HE support) • LN2 storage for CERN experiment: • Present situation: 2 x 20000 l (Compass and NA61) rented 12 kCHF each per year, for more than 10 years, i.e. more than 240 kCHF already spent. • Cost of a storage vessel: 120 kCHF • Proposal: Purchase 2 units (240 kCHF + EN-HE suppport)

  14. Additional proposals for general cryogenic services (II) • Recovery compressors (Helium, 200 bar) • Present situation: 3 compressors • 1 Burckhard compressor 400 m3/h very reliable • 2 Bauer compressor 100 m3/h requiring heavy corrective maintenance (20 kCHF/year over 5 years) and with low running hours (1500 h/y in average instead of 4000 h/y), i.e. the large Burckhard compressor is running often at reduced capacity to compensate the unavailability of the Bauer machines  Efficiency issue and additional wear (number of stop and go). • Proposal: Replace the 2 Bauer compressors by a new Burckhard 200 m3/h  350 kCHF

  15. Summary table *: According to TE-CRG

More Related