EDS 3 Release 5: SCED

EDS 3 Release 5: SCED. Phase 1 Kickoff Meeting. August 1, 2007. Agenda. EDS 3 Phase 1 Objectives EDS 3 Phase 1 Timeline EDS 3 Phase 1 Details Team Roles Preparation & Execution Q&A. Phase 1 Objectives.

platt
Télécharger la présentation

EDS 3 Release 5: SCED

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EDS 3 Release 5: SCED Phase 1 Kickoff Meeting August 1, 2007 http://nodal.ercot.com 1

  2. Agenda • EDS 3 Phase 1 Objectives • EDS 3 Phase 1 Timeline • EDS 3 Phase 1 Details • Team Roles • Preparation & Execution • Q&A http://nodal.ercot.com 2

  3. Phase 1 Objectives • Verify QSE’s ability to use Web Service interfaces to submit, modify, cancel, and retrieve three part offers, COP, output schedules, and Inc/Dec Offers (DSR only) • Verify QSEs understanding of SCED input validation rules • Use both the User Interface and Web Services interfaces for SCED inputs http://nodal.ercot.com 3

  4. Phase 1 Audience • Contact eds3@ercot.com if: • You should not be on this list • You should be on this list but are not http://nodal.ercot.com 4

  5. Texas Nodal Program Summary Release Schedule High Level Version 2.0 http://nodal.ercot.com 5

  6. SCED Phase 1 Sandbox and EDS Timeline • Nodal SandBox: Contains External Web Services pertinent to SCED. Verify your connectivity and are successful with requests. For support contact eds3@ercot.com http://nodal.ercot.com 6

  7. SCED Phase 1 Timeline • QSE’s with Resources must Register by 8/8/07 for a Testing Window • Testing windows available between August 24th and October 4th • Use of EWS and the MMS UI will be demonstrated during the testing window http://nodal.ercot.com 7

  8. SCED Phase 1 Timeline SCED Phase 1 Timeline with Example Activity Timeline EDS TIMELINE Example Activity Timeline http://nodal.ercot.com 8

  9. SCED Testing Phase 1 • QSE with Resources will sign up for a seven day testing window in the EDS environment • This will initiate a number of events that will occur before the testing window (detailed on slide 13) • The testing window begins with a two hour support call with online SME support from ERCOT • Goal is to provide immediate assistance to resolve issues • After the support call, QSEs with resources can execute additional scenarios they have “defined” • Support calls will be reserved in the order requests are submitted • Taking an earlier testing window enables more time for re-testing should it be needed • MPs that sign up for the first week of October will not have a 7 day testing window and almost no time to correct issues http://nodal.ercot.com 9

  10. Support Calls • Support Calls will be held Tuesday, Wednesday, and Thursday • Support calls occur twice daily: 9am – 11am and 1pm – 3 pm • Monday and Friday are reserved for issue correction, follow-up calls, and market wide status calls • Calendar is Posted on the Readiness Center • 37 slots are available on the following dates: http://nodal.ercot.com 10

  11. SCED Phase 1 Calendar http://nodal.ercot.com 11

  12. Sign-up Email Content The sign-up Email from QSEs with Resources should include: • Primary Contact Name • Primary Contact Email and Telephone • Support Window Date and AM or PM preference • Provide top three preferred dates • DUNS number of QSEs & sub-QSEs that have resources associated with them • Confirm that the server used to conduct SCED testing resides in the same data center where production will be hosted: Yes/No • Confirm that you the QSE will be engaged in testing and not your 3rd Party Service Provider: Yes/No • Send sign-up email to eds3@ercot.com by August 8th http://nodal.ercot.com 12

  13. Phase 1 - Preparation and Execution activities Draft http://nodal.ercot.com 13

  14. Preparation Execution Checklist Draft This Checklist will be completed by the Execution PM and consolidated to the Readiness Scorecard http://nodal.ercot.com 14

  15. Support Window Test Cases * See EDS Phase 1 Test Scripts document ** Inc & Dec required only for QSEs qualified to schedule DSR resources. http://nodal.ercot.com 15

  16. EDS 3 Execution - Organization http://nodal.ercot.com 16

  17. Readiness Metrics and Scorecard: SCED Phase 1 • MP2: QSEs with Resources Connectivity to EDS Environment • Expected completion date October 5 • MP3: QSEs with Resources Upload of SCED Offers to EDS • Expected completion date October 5 • Sign-Up Status • QSE signs up by 8/8 – Status is GREEN • QSE’s that have not signed up by • 8/9/07 – Will turn Amber until signed up • 10/5/07 – Will turn red • Execution • MP’s that have met readiness metric M2 and M3 by 10/1 are GREEN • MP’s that have attempted readiness metric M2 and M3 by 10/1 are AMBER • MP’s that have not yet attempted readiness metric M2 and M3 by 10/2 are RED http://nodal.ercot.com 17

  18. Phase 1 Dashboard Phase 1 Dashboard Draft http://nodal.ercot.com 18

  19. Digital Certificates • 1 digital certificate with a generic employee name has been generated for each QSE and sub-QSE with Resources. • The MP’s USA does not need to take any action • This is the only certificate that will work in the EDS environment • This certificate will also work in the Nodal Sandbox environment • It will not work in production, MOTE, or any other ERCOT environment • Distribution will occur after the QSE signs up for a SCED Phase 1 Testing Window • Once the Nodal Market Participant Identity Management System is operational, these generic EDS certificates will be revoked. • All valid ERCOT issued digital certificates will continue to work in the Nodal Sandbox. http://nodal.ercot.com 19

  20. Issue Management • Issues encountered on the Support Call will have a high priority • Issues encountered during the remainder of the Test Window should be reported via the form (http://nodal.ercot.com/readiness/eds3/documents/genkd/ERCOT%20EDS%20Issue%20Submission%20Form.xls) and submitted to eds3@ERCOT.com • Internal testing will occur in parallel with EDS 3 Phase 1 • MP issues will be logged when submitted • MP submitted issues will be compared to internal defects after internal testing is completed • When completing the Issue form, provide the files used and the sequence of file submission (per slide #9 “defined”) http://nodal.ercot.com 20

  21. EDS 3 SCED Phase 2 • TPTF Approved the “EDS3 Release 5 – SCED Testing Establishing Generating Resource Offer Curves v1.0” document • This meets the ERCOT Nodal Transition Plan section 5.4.1 (1) requirement • QSEs with Resources need to read this document and provide ERCOT (via eds3@ERCOT.com) with the completed spreadsheet • Due date is August 10th http://nodal.ercot.com 21

  22. Relevant reference documents http://nodal.ercot.com 22

  23. Activity Summary • Email eds3@ercot.com if there is an issues with slide 5 “Phase 1 Audience” • Email eds3@ercot.com with the information on slide 12 “Sign-up email” by August 8th • Read the “EDS3 Release 5 – SCED Testing Establishing Generating Resource Offer Curves v1.0” and submit the spreadsheet to eds3@ercot.com by August 10th • Use the Nodal Sandbox functionality http://nodal.ercot.com 23

  24. Q&A http://nodal.ercot.com 24