1 / 15

Método de Ven Te Chow

Método de Ven Te Chow. Engenheiro Plinio Tomaz. Método de Ven Te Chow. Método de Ven Te Chow , 1962 DAEE e PMSP Até 50km 2 Qp = Qb + 0,295. ( he/ t) . A . Z Sendo : Qp = vazão no tempo t em m 3 /s Qb = vazão base na bacia no ponto considerado em m 3 /s

prince
Télécharger la présentation

Método de Ven Te Chow

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Método de Ven Te Chow Engenheiro Plinio Tomaz

  2. Método de Ven Te Chow • Método de Ven Te Chow, 1962 • DAEE e PMSP • Até 50km2 • Qp= Qb + 0,295. ( he/ t) . A . Z • Sendo: • Qp= vazão no tempo t em m3/s • Qb= vazão base na bacia no ponto considerado em m3/s • he= chuva excedente em milímetros calculado pelo Método do número da Curva CN do SCS • t= duração da chuva excedente em horas, Conforme PMSP, 1998 devemos pesquisas várias durações de t e escolher aquela que conduz à maior vazão de pico Qp. • A= área da bacia em km2 • tp= tempo de retardamento em horas, que é o tempo compreendido entre o centro de massa da chuva excedente e o pico do hidrograma unitário. • 0,295= resulta da multiplicação de K=1,06 vezes 0,278 • Z= fator de redução de pico dado pela equação:

  3. Fator de redução Z e tp • Z= 0,0037 + 0,8854. ( t/ tp) - 0,2684 . (t/tp)2 + 0,0378 . (t/tp)3 • tp= 0,005055 . (L / S0,5)0,64 • Sendo: • L= comprimento do álveo desde o divisor de águas até a secção de controle em metros. • S= declividade média do álveo em porcentagem. • tp= tempo de ascensão em horas • tp=0,6 tc (SCS)

  4. Número da curva composto • CNw = CNp . ( 1-f ) + f . (98) • Sendo: • CNw = número CN composto da área urbana em estudo; • CNp = número CN da área permeável da bacia em estudo e • f= fração da área impermeável da bacia em estudo.

  5. Chuva excedente Q (mm) • ( P- 0,2S ) 2 • Q= -------------------------- válida quando P> 0,2 S • ( P+0,8S ) • 25400 • sendo S= ------------- - 254 • CN

  6. Equação de chuva Intensa • 1747,9 . Tr0,181 • I =------------------------ (mm/h) • ( t + 15)0,89

  7. Equação de Paulus • Párea = Pponto . k • onde: • Párea = precipitação na área • Pponto = precipitação no ponto • Ao= 25km2 • K = 1,0 – [ 0,1 . log (A / Ao ) ] • Se a area A for menor que 25km2 então K=1.

  8. Exemplo: Ven Te Chow • Calcular para RMSP bacia A=11,2km2 Tr=100anos, usando equação de P.S.W. Dado talvegue L= 7040m e S=0,722%. Fração impermeável f=0,50. • tp= 0,005055 . (L / S0,5)0,64 • tp= 0,005055 . (7040 / 0,7220,5)0,64 • tp=1,63h • tp=0,6 tc Portanto • tc= tp/0,6= 1,63/0,6= 2,67h

  9. Exemplo: Ven Te Chow • CNw = CNp . ( 1-f ) + f . (98) • CNw = 60 . ( 1-0,50 ) + 0,5 . (98)= 79 • 25400 • sendo S= ------------- - 254 • CN • 25400 • sendo S= ------------- - 254 = 67,52mm • 79

  10. Exemplo: Ven Te Chow • 1747,9 x 1000,181 • I =------------------------ (mm/h) • ( t + 15)0,89 • Duração das chuvas: 0,8h, 1h, 1,25h 1,5h 2,0h, 2,5h • Supondo duração da chuva de 2h então t= • 2h= 2,0x60=120min • I= 51,11mm/h • Em 2h P= 2 x 51,11=102,22mm

  11. Exemplo: Ven Te Chow • ( P- 0,2S ) 2 • Q= -------------------------- • ( P+0,8S ) • Supondo chuva de 2h teremos P=102,22mm • ( 102,22- 0,2x67,52 ) 2 • Q= ------------------------------------= 50,38mm=he • ( 102,22+0,8x67,52)

  12. Exemplo: Ven Te Chow • Z= 0,0037 + 0,8854. ( t/ tp) - 0,2684 . (t/tp)2 + 0,0378 . (t/tp)3 • t/tp= 2,0h/ 1,60h= 1,229 • Z= 0,0037 + 0,8854. ( t/ tp) - 0,2684 . (t/tp)2 + 0,0378 . (t/tp)3 • Substituindo t/tp= 1,229 achamos • Z= 0,76

  13. Exemplo: Ven Te Chow • Qp= Qb + 0,295. ( he/ t) . A . Z • Qb=2 m3/s • Qp= 2+ 0,295x ( 50,38/ 2,0) x 11,2 x 0,76 • Qp= 67m3/s • Nota: fizemos para chuva de D=2h, mas podemos fazer uma curva com chuvas variando de 1h, 1,25h 1,5h 2,0h, 2,5h e 3h e teremos um hidrograma

  14. Hidrograma obtido pelo Método de Ven Te Chow

  15. Fonte: • Está no site www.pliniotomaz.com.br • Em Complementos do Livro Cálculos Hidrológicos e Hidráulicos para obras municipais. • Engenheiro Plinio Tomaz • E-mail: pliniotomaz@uol.com.br