This document outlines the planning and execution of the dismounting of current Beam Loss Monitors (BLMs) and the installation of new BLMs at the LHC facility. It details the scheduled warm-ups, powering tests, and cool-down procedures required for the effective integration and performance assessment of the superconducting circuits. Key activities are scheduled over multiple months focusing on preparation, installation, and testing phases to ensure optimal performance and safety of the LHC systems.
E N D
ARC: Dismounting of current installed BLMs ARC: Installation of existing and 2 more BLMs ARC: RSM
Splices PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Splices Splices Splices Preparation for cool-down Splices Powering Tests Warm-up Cool-down Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Jean-Philippe : “LHC consolidation of the superconducting circuits ” K. Foraz - LHC Performance Workshop 2012
Splices Dismounting BLM: Dec,Jan,Feb PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Splices Splices Splices RMS Powering Tests Preparation for cool-down Splices Warm-up Cool-down Installation BLM: Aug,Sep,Oct,Nov Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Jean-Philippe : “LHC consolidation of the superconducting circuits ” 8 weeks during the night for RSM : Dec,Jan2014 K. Foraz - LHC Performance Workshop 2012