This study guide includes essential topics and details for the upcoming exams on May 7th. It covers critical route analysis, PERT calculations, and project deadline probabilities. Specifically, it delves into the shortest route scenario using given parameters and analyzes tasks A through F for slack times. Additionally, it emphasizes understanding the critical path through clear examples. Note that the class demo differs from the assignment requirements, and activities should be presented in memo format.
E N D
Set 7 due today • Set 8 due April 18 • C-3 due April 18 • Exam May 7
50 B M 15 10 55 P V 60 L 20 125 S
Delete both M-B,V-B • L-S 125 • L-P 60 • L-P-M 70 • L-P-V 115 • L-P-M-B 120
Answer to (2) PERT
A 4 1 E B 3 C D F 2
ANSWER TO (a) E(x)=12
ANSWER TO (b) CRITICAL PATH: C-D-E
NORMAL TABLE • Kinderman Supplement, p 58 • Row 1.0 • Col .00
Answer to (c) P(finish project before deadline)= .84
Excel • Class demo NOT same as assignment should be in memo format • Describe critical activities in sentence