1 / 11

IGS Real Time Pilot Project: Analysis Centre Activities

IGS Real Time Pilot Project: Analysis Centre Activities. Loukis Agrotis 4 June 2008. Objectives Schedule Analysis Centre Status RT Processing Issues and Challenges Conclusions. Outline. Objectives.

redford
Télécharger la présentation

IGS Real Time Pilot Project: Analysis Centre Activities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IGS Real Time Pilot Project: Analysis Centre Activities Loukis Agrotis 4 June 2008

  2. Objectives Schedule Analysis Centre Status RT Processing Issues and Challenges Conclusions Outline

  3. Objectives • Generation and Dissemination of a Real Time Combination Product • Accurate (clocks < 0.5 ns, predicted orbits <5 cm ) • With low latency ( <? ) • 5-10 sec from observation time should be achievable • High Availability • Low Downtime • Available to a potentially large user set • High Reliability • But with no “service guarantees” • These are for commercial providers to offer

  4. April 08: AC teleconferences and formal PP kick-off June 08: Clock RINEX and SP3 Products from 3 ACs Start routine comparisons Develop and validate tools for combination solution Prototype process on ESOC FTP server (to be eventually transitioned to CDDIS) July 08: Start Disseminating Comparisons Sept 08: Batch Combination Product Jan 09: RT Product Dissemination by ACs All ACs Operational March 09: RT Combination Product Available Schedule

  5. Analysis Centre Status

  6. Analysis Centre Status

  7. Issues and Challenges Product and Data Formats • Formats for RT products • Formats still to be defined and agreed • Main issue that could hold back progress of RT PP • Formats for Data • Predominant data formats are RTCM, RT-IGS / SOC and BINEX for GPS • Main challenge for data formats is support for generic GNSS (GLONASS, Galileo, Compass) and higher accuracies • Discussions now taking place on future requirements thanks to the good efforts of NRCan and BKG • Objective is to find the best fit among currently proposed format revisions and to influence their evolution so that our requirements are met. • Transport Protocols • NTRIP via HTTP, TCP or UDP • UDPRelay • Either or both could be used to disseminate the RT Combination Product

  8. Issues and Challenges Network Issues • Excellent results are possible thanks to the contributions of a number of agencies • Large area with no network coverage results in network fragmentation. Example from 22 April shows circled stations and satellites which experienced jumps in our solution. • Densification of the network is being actively pursued

  9. Issues and Challenges Network Issues • The clock correction plots show that all clocks in the South-East have jumped by the same amount, while the remaining clocks were unaffected • Several similar occurrences of this phenomenon have been observed

  10. Issues and Challenges Filter Tuning Issues • Jump experienced in PRN19 at start of new pass with CAS1 • CAS1 clock appears to reset with each new pass • Changes needed to the tuning of the filter so that the CAS1 clock behaviour is better modelled

  11. Conclusions • RT PP is now active, thanks to the enthusiasm and support of the participating groups, particularly NRCan and BKG. • Success of the AC activity relies on the generation of high quality RT products but also on making the correct decisions on formats and protocols to ensure a wide distribution • Densification of the network in areas of low coverage is a priority • An IGS RT service will complement and increase the usefulness of the various commercial offerings for this type of service - it should not be viewed as competition to any of the current offerings of potential participants.

More Related