An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Report on OPERA Emulsion Nakamura M. Nagoya 2006,Dec.7

  2. OPERA • Emulsion-Counter Hybrid Experiment • Large Scale Emulsion film production is the key to establish the experiment. Need Strong Collaboration with Fujifilm

  3. Overview of the Fujifilm – NagoyaCollaboration for OPERA • Started the Study of Gel dilution (Nishiyama)- (Kotaka, Teraoka) 1998 Started the Study of Machine coating Film Production and Refreshing FUJI NAGOYA KANAZAWA Yuji NAKAMURA M. (Nishiyama,Kuwabara)- (Fukuda,Nada) 1999 July Succeeded to produce machine coated emulsion film in the real production line.→Realize OPERA

  4. Overview of the Fujifilm – NagoyaCollaboration for OPERA 2001 May Succeeded to realize Refresh-able Emulsion (Kuwabara) - (Taku NAKAMURA, Uetake) Start the R&D of Refreshing Facility 2003 Jan Started construction of Refreshing facility 2003 Apr Started OPERA film Mass production 2003 Nov Started Refreshing 2004 Dec First shipment of Refreshed Emulsion film to Gran Sasso

  5. Mr. Yuji KANAZAWAResponsible Person of OPERA project in Fujifilm Deceased Aug. 14, 2006

  6. Current Status • Re-started refreshing in this October. (Leading by Naka, Yoshioka, Yoshida) • Next Shipment to GS at the end of Dec. • Finish refreshing: End of March 2007

  7. Amount • Already Shipped : 130600 Bricks (Reference: Full installation : 64 x 52 x62 Wall = 206336 Bricks) • Under treatment: 26850 Bricks • Films under investigation: Treated at the early stage of Refreshing Facility: ~ 2770 Bricks (High Fog and Low GD) Not refreshed but at GS: 890 Bricks (Will be refreshed at GS?? ~4 weeks Job) • Others Films for PEANUT : 360 bricks Films for Test experiments : ~ 70 bricks Films for BAM : ~ 200 bricks Wasted by troubles etc ~ 30Bricks Process Monitoring films ~ 100 Bricks

  8. Summary • We have not yet finished the Refreshing, but we are approaching to the “Goal”. (March 2007) • I wish to express special thanks to the People of Fujifilm working with us. especially KANAZAWA-san • We, all Nagoya people working on Emulsion Film R&D and Production Job, are happy to hear that the BAM started the Brick production and will install all of our films until the Spring of 2007.