Items Announced in Budget 10-11 Gauge Conversion in NGP Divn. Targeted works 2010-11.

ON GOING PROJECTS. Items Announced in Budget 10-11 Gauge Conversion in NGP Divn. Targeted works 2010-11. DOUBLING. Items Announced in Budget 10-11. Item No. 116 ( XXIX) of Budget Speech Durg – Rajnandgaon 3 rd line ( 30.889 Km) STATUS Cost of project - ` 147.06 Crores.

rigg
Télécharger la présentation

Items Announced in Budget 10-11 Gauge Conversion in NGP Divn. Targeted works 2010-11.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ON GOING PROJECTS • Items Announced in Budget 10-11 • Gauge Conversion in NGP Divn. • Targeted works 2010-11.

  2. DOUBLING Items Announced in Budget 10-11 • Item No. 116 ( XXIX) of Budget Speech • Durg – Rajnandgaon 3rd line ( 30.889 Km) STATUS • Cost of project - `147.06 Crores. • Budget Grant - `10.00 Crores. for 2010-11 • Detailed estimate sanctioned in Oct. 10. Contd…

  3. New Gauge Conversion works • Item No 115 (i) Budget speech • Chhindwara -Nainpur – Mandla Fort (182.25 Km) STATUS • Cost of project - ` 556.54 Crores. • Budget Grant for 10 - 11: ` 1.00 Crores. • Detailed part estimate of NIR - MFR for ` 145.8 Cr. Prepared. Contd…

  4. Completed Gauge Conversion Project • Item No 113 (x) of Budget speech • Gondia - Balaghat including MOIL siding (42+7 Km) section commissioned in year 2005 • Balaghat - Katangi [46.8] - Section completed & commissioned on 7.05.2010 Contd…

  5. New line Project • Item No 111 of Budget speech • Mandir Hasaud - Naya Raipur (20.00 Km) sanctioned as material modification to Raipur – Titlagarh doubling of East Coast Railway • Cost of project - ` 77.32 Crores. • Budget Grant for 2010-11 – Nil • Part estimate for ` 28 Lakhs. for preliminary activities sanctioned by GM/SECR. Contd…

  6. Updating of Socially Desirable Rail Connectivity Proposals • Item No 102 of Budget speech (Sr. No.10) • Barwadih- Chirimiri / Ambikapur[182km] • RET Survey report submitted on 17.05.03 for ` 406.86 Crs. with ROR (-) 4.85%. Updating done on 16.2.09. with ROR (-) 9.05%. Board again desired for updating. Updated estimate under finance vetting.. Contd…

  7. Updating of proposalsLohardaga-Korba (326 Km.)(via Dharmjaygarh & Pathalgaon) • Item No 102 of Budget speech (Sl No. 63) • Report Submitted to Rly. Board in 2003. • Cost ` 621.67 crores & ROR (+) 07.25 %. • Updated estimate under calculation of ROR. Contd…

  8. Updating of proposalsPendra Road –Korba/Gevra Rd. (121.7 Km.)(via Pasan, Sundargarh & Deepika) • Item No 102 of Budget speech (Sl. No. 82) • PET survey sanctioned in 1996-97. • Report submitted to Board in 2003. • Cost ` 344.43 Crores & ROR (+)15.23%. • Updated estimate under finance vetting. Contd…

  9. Updating of proposalsRaigarh - Mand Colliery to Bhupdeopur(63 Km. with Fly over) • Item No 102 of Budget speech (Sl. No. 88) • PET survey sanctioned in 2008-09. • Report submitted to Railway Board in July -2009 at the cost of ` 310.64 Crores & ROR (+) 29.58% • Updated report submitted to Board in Aug. -10 at the cost of ` 344.20 crores and ROR (+) 26.33% Contd…

  10. Updating of proposalsRaipur – Jharsuguda (310 Km.)(via. Kharotapalan, Baloda Bazar, Bhatgaon & Sarangarh.) • Item No 102 of Budget speech (Sl. No. 89) • RET survey sanctioned in 1999-2000 • Report submitted to Railway Board in Feb-2003. • Cost ` 971.96 crores & ROR (-) 20%. • Updating of abstract estimate is being done. Contd…

  11. Updating of proposals Ramtek – Gotegaon(275 Km.)(via Khawasa, Sioni & Dhuma) • Item No 102 of Budget speech (Sl. No. 92) • RET survey sanctioned in 1995. • Report submitted to Railway Board in April 1999. • Cost `. 528.21 crores & ROR (-) 11.50% • Updating in progress. Contd…

  12. Updating of proposals • Item No 118 (i) of Budget speech • Wadsa - Desaiganj - Gadchiroli - 49.5 Km(Cost sharing) • RET survey sanctioned in Aug -1995. • Initial report submitted in July - 1998. • Updated report submitted in Aug - 2010. • Cost ` 232.40 crores & ROR without sharing (-) 3.88% & with 50% cost sharing by State Govt. ROR (-) 0.40%

  13. Gauge conversion in NGP division

  14. Planning of N.G. conversion in NGP Divn.

  15. Contd.

  16. Progress of Major ItemsJabalpur – Nainpur - Balaghat

  17. Contd. Progress of Major ItemsJabalpur - Sukarimangla

  18. Contd. Progress of Major ItemsNagpur - Chhindwara

  19. Contd.

  20. Targeted works 2010-11

  21. Contd…

  22. Contd…

  23. Contd…

  24. Contd…

  25. PROGRESS OF QUARTERS

  26. Contd.

  27. THANK YOU

  28. WORKS COMPLETED IN 2009 -10 & 2010 -11 (PB)

  29. Contd.

  30. STATUS OF LAW BOOK WORKS

  31. Contd.

  32. Contd.

  33. WORK IN PROGRESS In. Crs. Remarks ESP & IP approved. Slewing of main line and major OHE alterations completed. PF extension work completed except stone surfacing.

  34. Contd. In. Crs. Remarks Existing relay room will be used. 100 % E/W, bridge work and ballast supply completed. FOB - 100 % & Linking 60%. OHE - 48 foundation out of 53 done & 28 mast erected, steel received. S & T progress - 80%. CRS sanction obtained.

  35. Contd. In Crs. Remarks Work is planned in two stages. Stage -I – Up loop and one Dn loop work at KDTR. Stage – II – 2nd Dn loop. Connection for all 3 loops planned for simultaneous commissioning to avoid redundant works. CRS sanction awaited. E/W – 95%, Building & Bridge work – 100%, S & T – 95%, Track Linking in progress.

  36. Contd. In. Crs. • Completed work • Formation, track, extension of culvert. • Shed (40x12) 140 ton for crane. • S & T goomty (3mx3m) & Inspection pit. • Balance work in progress • Service building for C&W staff – Upto plinth level completed. • SIP & SWR to be revised after ESP alteration due to U/M LC in yard to be manned & relocation of point. • CRS sanction for D cabin submitted on 20.09.10

  37. Contd. In. Crs. • Goods platform work nearly completed. • Placement/withdrawal of trains being done from BSP end. • Connectivity from NGP end should be done along with 3rd line bet. Durg – Rajnandgaon to avoid repeated NI and yard modification. • Renovation of existing shed for labour rest room and merchant room in progress.

  38. In. Crs. Contd. Full quantity of cable procured. Electrical work completed. MDH-URK commissioned on 28.7.09.Tender awarded for Dadhapara - Belha section. Work in progress.

  39. Contd. In. Crs. Remarks Work proposed for dropping.

  40. Contd. In. Crs. Remarks ESP Approved. Cost of work is exceeding the abstract estimate substantially. Detailed estimate is under revision.

  41. Contd. In. Crs. Remarks Scope of work revised. ESP approved. Estimate sanctioned. Civil tender finalised recently. OHE tender finalised. S & T tender opened on 05.02.10 and discharged. Fresh tender opened on 20.08.10 and under finalisation.

  42. Contd. In. Crs. Detailed estimated sanctioned. Tender awarded & work under progress. SWR’s pending in division. TDC Dadhapara - Belha - Oct-10 Jairamnagar - Latia - Nov-10 Gatora - Jairamnagr - Nov-10 BSP - Gatora - Dec-10

  43. Contd. In. Crs. Remarks Land acquisition required at JSG end land plan submitted. Revised ESP approved. Land acquisition proceedings stalled. Work to be truncated to avoid land acquisition and revised ESP prepared & under finalisation.

  44. Contd. In. Crs. S & T and OHE tender finalised. E/W in progress. One high tension tower in the alignment is yet to be dismantled by CSEB.