1 / 12

Agenda and Background

ANSI-NIST Nuclear Energy Standards Coordination Collaborative David Matthews, Director, Division of New Reactor Licensing Larry Burkhart, Chief, AP1000 Projects Branch NRC’s Office of New Reactors July 23, 2013. Agenda and Background. Agenda

ronald
Télécharger la présentation

Agenda and Background

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ANSI-NISTNuclear Energy Standards Coordination CollaborativeDavid Matthews, Director, Division of New Reactor LicensingLarry Burkhart, Chief, AP1000 Projects BranchNRC’s Office of New ReactorsJuly 23, 2013

  2. Agenda and Background Agenda • Background on status of AP1000 design review and licenses • New Reactor Designs/applications in the USA • Quick construction status – Vogtle and Summer AP1000s • Part 52 and lessons learned from a regulatory perspective Background • Combined license – NRC authorization to construct and operate a nuclear power plant in accordance with applicable laws, regulations, and conditions • Latest version of Westinghouse’s AP1000 standard design certified in December 2011 • SNC, et al, received combined licenses for Vogtle Units 3 and 4 on February 10, 2012 • SCE&G, et al, received combined licenses for Summer Units 2 and 3 on March 30, 2012 • First Nuclear Concrete (FNC) for Summer Unit 2 poured 9 – 11 March 2013 • FNC for Vogtle Unit 3 poured 12 – 14 March 2013 • 4 AP1000s under construction in China (Sanmen and Haiyang sites commenced in 2008) – cooperation with China bilaterally and multilaterally • AP1000 design reviewed/under review in Canada, China, and the U.K. (MDEP)

  3. New Reactor ApplicationsUnder Review – Large LWRs+ ABWR AP1000 ESBWR EPR USAPWR 3 +Large LWRs-- Large Light-Water Reactors, generally of the order of 1000 MW(e) or more

  4. Construction Status Vogtle • Vogtle Unit 3

  5. Pre-Construction Construction Verification Early Site Permit LWA Combined License Review, Hearing, and Decision Verification of Regulations with ITAAC Reactor Operation Decision Optional Pre-Application Review Standard Design Certification Part 52 - Fitting the Pieces Together • Licensing decisions finalized before major construction begins • Inspections w/ITAAC (Inspections, Tests, Analyses, and Acceptance Criteria) to verify construction • Limited work may be authorized before COL issuance

  6. Lessons Learned in COL Reviews • First implementation of NRC’s 10 CFR Part 52 processes to issue COLs • Bipartisan Policy Center Report (April 6, 2010) • Thorough and timely evaluation of license applications…however, there were expected problems in navigating the new processes • The Commission should ensure the lessons learned are rigorously applied to make the processing of subsequent applications more efficient • NRC’s Lessons Learned Review Report – April 213 • High quality applications with sufficient detail • Timely development and maintenance of regulatory guidance • Strong design standardization • Early identification and timely resolution of complex issues • Improve system of requests for additional information • Concurrent reviews of design certifications and combined license applications • Update to regulations incorporating lessons learned

  7. Current Licensing Basis Definition of Licensing Basis (10 CFR 54.3) Obligations (Regulations, License Conditions, Technical Specifications, Environmental Protection Plan, and ITAAC) Mandated Licensing Basis Documents (FSAR, QA, EP, Security Plan, etc.) Vogtle/Summer-FSAR: Summer — COL FSAR +Plant Specific DCD Vogtle — ESP SSAR + COL FSAR + Plant Specific DCD

  8. FSAR COL FSAR ESP SSAR (Vogtle Only) Plant –Specific DCD Tier 2* E Plans QA Security Op Programs FFD E Plans Seismic Hydrology Tier 1 Tier 2

  9. Experience post-COL Issuance • First implementation of Part 52 processes (licensing basis maintenance) • License amendment (LARs), and exemptions, and ASME code relief requests • LARs are expected as design evolves and due to in-situ conditions • Design changes to rebar (shear reinforcement details) • Turbine building bracing • Additional electrical penetration assemblies in the containment • Inconsistencies between Tier 1 and Tier 2 • Other • Preliminary Amendment Request (PAR) Process • Codified in license as an option for the licensee (following ISG-25) • Flexibility in making physical changes while licensing basis change is udner review • Tied to an LAR • Obligation to construct in accordance with the licensing basis • NRO is performing a self assessment of the experience during the first year of licensing Part 52 plants (with input from licensees, vendors, public, staff)

  10. Summary • First implementation of Part 52 regulations to issue COLs and for post-licensing processes • Vogtle and Summer licenses issued and construction ongoing • Experience gained in licensing pre and post COL isance • A learning experience for regulator and licensee • Improvements can be made • Assessments to inform improvements • Philosophy of Part 52 – Standardization • Importance of maintaining current licensing basis • Managing changes appropriately • Proper change processes • Safety benefits • ITAAC completion • Safe operation OFFICIAL USE ONLY

  11. 10 CFR Part 52 QUESTIONS? www.nrc.gov/new-reactors/col-holder/html

  12. ACRONYMS • CLB – current licensing basis • COL – combined license • DCD – design control document • EP – emergency plan • ESP – early site permit • FFD – fitness for duty • ITAAC – inspections, tests, analyses, and acceptance criteria • LAR – license amendment request • LWA – limited work authorization • LWR – light water reactors • SMR – small modular reactor • SSAR – site safety analysis report • UFSAR – updated final safety analysis report OFFICIAL USE ONLY

More Related