1 / 20

Mechanical Systems

Gamma-ray Large Area Space Telescope. Mechanical Systems. GLAST Large Area Telescope: Marc Campell SLAC Subsystem Manager marcc@slac.stanford.edu (650) 926-4658. Overview – MECH SYS Responsibilities. Grid Box Base Assembly (GBBA)

ronna
Télécharger la présentation

Mechanical Systems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope Mechanical Systems GLAST Large Area Telescope: Marc Campell SLAC Subsystem Manager marcc@slac.stanford.edu (650) 926-4658

  2. Overview – MECH SYS Responsibilities • Grid Box Base Assembly (GBBA) • Grid + Radiator Mount Brackets + Top Flange Heat Pipes + Thermal Control hardware • Configuration delivered to I & T for LAT integration • Grid Box Assembly (Qual unit only) • Grid #2 is Qualification unit • GBBA + EMI Skirt + Dummy CAL Baseplates • Combined Grid Static Load and LAT strength test • Radiators • Fabricated and tested by LM • X-LAT Plates • Fabricated and tested by LM

  3. 1.6 m 1.6 m .24 m Mechanical Subsystems Overview 4 x 4 Grid >> Grid Box Base Assy >> Grid Box Assy Test Configuration (CAL Baseplates not shown) Shear Plates TFHP EMI Shields Radiator Mount Brkt TCS Hardware

  4. Radiator Panel - Exploded View Variable Conductance Heat Pipe FOSR Honeycomb Core Outer Facesheet Doublers 1.56 m Z Y X Inner Facesheet Reservoir 1.82 m Reservoir Support Bar

  5. +Z +Z Radiator & X-LAT Placement Top Flange Heat Pipe 3 Way Heat Pipe Joint Down Spout Heat Pipe X-LAT Heat Pipe

  6. Recent Accomplishments Grid Box • Grid #1 rough machining complete • Grid #1 finish machining 50% complete (shown below) • Grid #2 rough machining & heat treat complete

  7. Recent Accomplishments (cont) Lockheed Martin • Downspout Heat Pipes complete (shown below) • Top Flange Heat pipes complete • Radiator detail parts fabrication 20% complete

  8. Mechanical Systems Critical Path Flight Hardware for TCS 6/30/04 / 0 Grid Box Base Assembly #1 Operations 7/22/04 / 0 Flight Grid RFI #1 7/22/04 / 0 GBA Assembly fixtures/ MGSE 6/30/04 / 0 Fabricate Flight Grid (4X4) #1 6/15/04 / 0 Inspect Flight Grid, EMI skirt, details #1 06/16/04 / 0 GBA #1 Fit Check Operations 6/30/04 / 0 Fabricate EMI skirt, Grid details) #1 6/15/04 / 0 Inspect Flight Grid, EMI skirt, details #2 9/3/04 / 0 Fabricate Flight Grid (4X4) #2 8/27/04 / 0 Grid Box Assembly #2 Operations 10/18/04 / 0 Static Load Test Complete 12/16/04 / 0 Completion Dates/Variance to Baseline

  9. Rationale for Second Grid • LAT Sine Burst (Strength) Test deleted Fall 2003 • Concerns about over-testing LAT • Objectives could be met by adding test cases to Grid Static Load Test • Results approximately 1 year earlier • Reduced LAT schedule • Grid Static Load plan changed during Re-baseline • Original plan was to rough machine second grid and hold as flight spare • Re-baseline plan completes machining of second Grid and components required to complete Grid Box Assembly • Perform test on second grid as a Qualification test • Pulled delivery of Flight unit (Grid #1) forward approximately 2 months and maintain delivery to I & T milestone

  10. Radiator Critical Path VC Heat Pipe Fab 5/19/04 / 0 Radiator Assy Complete 11/28/04 / 0 Radiator Details Fab 5/19/04 / 0 Protoqual Testing Sine Vibration Survey 12/15/04 / 0 Acoustic Test 1/28/05 / 0 Sine Vibration Survey 2/14/05 / 0 Thermal Vacuum / Balance Test 4/7/05 / 0 Deliver to SLAC 4/21/05 / 0 Completion Dates/Variance to Baseline

  11. X-LAT Plate Critical Path X-LAT Heat Pipe Fab 9/15/04 / 0 X-LAT Plate Assy Complete 10/29/04 / 0 P/Qual Thermal Vacuum Test 11/30/04 / 0 Deliver to SLAC 12/09/04 / 0 Completion Dates/Variance to Baseline

  12. Open Issues • Radiator VCHP Helium leak rate may impact ACD Photomultiplier Tubes (PMT’s ) • LM can substitute another inert gas, but it impacts ground (not on-orbit) performance. • LM given the “OK to Fab” the VCHP’s up to the charging operation (3rd week of April). • Dispersion analysis is underway to evaluate impacts to PMT’s. ECD: 4/16/04 • Coordination of TCS validation, LM Radiator Thermal Vacuum & Balance test plans • TCS risk assessment and Qual test plan requested by GSFC. ECD: 4/30/04 • TCS – location of Grid heaters, thermostats, RTD’s and associated wiring needs to be finalized (top assembly drawing) • ECD: 5/3/04 • Radiator integration sequence • Grid has been modified to allow integration via pure translation of the Radiators. • Demonstration and detailed procedure are in work. ECD: May 04

  13. Risk List

  14. Key Schedule Issues • Problem: Late changes to Grid interface requirements • Impact: Grid #1 delivery from Tapemation (vendor) • Is: 6/15/04; Re-Baseline: 3/30/04 • Mitigation steps taken or planned to get back on schedule: • Freeze Grid design (interfaces) and build it • Reduced Grid plating time 4 weeks by changing thermal requirement from 3 to 2 plating types (Alodine and Nickel plating – black anodize deleted) • Working with Tapemation to incorporate producibility improvements to design

  15. Key Schedule Issues (cont) • Problem: Late Grid delivery to SLAC drives delivery to I&T • Impact: Grid to I & T delivery date • Is: 7/22/04; Re-Baseline: 6/15/04 • Mitigation steps taken or planned to get back on schedule: • Static Load testing on second Grid established during re-baseline activity • Minimized Mechanical Systems assembly operations • Deleted Grid Box Assembly operations (fit check only) • Deleted Thermal Cycle testing of Grid Box assembly • Postponed some operations until after delivery to I&T

  16. Key Schedule Issues (cont) • Problem: Late start on fabrication of X-LAT Plate Assembly • Impact: Delays X-LAT Plate delivery date to SLAC • Is: 12/9/04; Re-Baseline: 8/12/04 • Mitigation steps taken or planned to get back on schedule: • Lockheed performing preliminary design to draft versions • Interfaces to DAQ boxes and Grid were defined • Lockheed will be given permission to build the X-LAT Heat Pipes prior to the Manufacturing Readiness Review

  17. Approved Cost Changes Since Rebaseline • (k$) • 4.1.8 Baseline, November 03 $13,384 • Changes: • Align Schedule w/ Grid Deliv $ (22) • Grid Assy & TCS Replan $ 53 • Stanford Benefits Rate Increase $ 63 • Total Change $ 94 • 4.1.8 Baseline, February 04 $13,478

  18. Variances Cost variances: • LM = +$158K. Will be used in upcoming months • SLAC = -$57K. For contractor engineering support. Schedule variances: • LM = zero • SLAC = -$189K. Receive flight hardware for thermal control system (-$184K)

  19. Looking Ahead 6 Months • Grid #1 delivered to I&T • Supporting I&T integration operations • Grid #2 delivered to SLAC • Static Load Test preparations underway • X-LAT Plate fabrication complete and ready for test • Radiator fabrication 75% complete

  20. Summary • Major interface issues have been resolved in last 6 months • CAL – Grid, X-LAT – DAQ and Tracker - Grid • Designs are released (except X-LAT plate) • Fabrication of both Grids is underway • Fabrication of Radiators is underway • LM effort has ramped up significantly • No major issues with hardware fabrication • Focus now on resolving test issues • MECH is off of the LAT critical path

More Related