1 / 9

Electron Systems Overview

Electron Systems Overview. David Schultz. 2 month delay in Injector Impact and plan Later talks to cover: Injector/Linac Management, E. Bong Injector/Linac Installation Status, C. Rago. Installation Schedule. 250 MeV. 4.30 GeV. 13.6 GeV. 6 MeV. 135 MeV. Linac- X L =0.6 m.

rstruble
Télécharger la présentation

Electron Systems Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Electron Systems Overview David Schultz • 2 month delay in Injector • Impact and plan • Later talks to cover: Injector/Linac Management, E. Bong Injector/Linac Installation Status, C. Rago

  2. Installation Schedule 250 MeV 4.30 GeV 13.6 GeV 6 MeV 135 MeV Linac-X L =0.6 m Linac-0 L =6 m rf gun L0-a,b Linac-1 L 9 m Linac-2 L 330 m Linac-3 L 550 m 25-1a 30-8c 21-3b 24-6d ...existing linac 21-1 b,c,d undulator L =130 m X BC2 L 22 m BC1 L 6 m ‘Wall region’ DL2 L =275 m 2007 down Now through Dec. SLAC linac tunnel research yard

  3. LCLS Installation and Commissioning Time-Line Drive-Laser Commissioning LTU/und. Install LTU/und. hall “ready” Drive-Laser Installed Controls Checkout First Spont. Light A S O N D J F M A M J J A S O N D J F M A M J J 2006 2007 2008 No Ops Gun/Inj./BC1 Install (8/21 – 2/20) Gun/Inj./BC1 Commissioning Inj./Linac/BC2 Commissioning linac/BC2 Install LTU/und. Commissioning Oct. 19, 2006

  4. 2006 Installation Sector 21 Sector 20 Laser stopper BLM BC1 LX L1 Ins/SAB Wall

  5. Linac Tunnel Installation Issues • Late: • Need to lock-up and begin Linac beam operations Jan. 2. • A few components will not make the lock-up deadline. • Vacuum chambers in insertion region. (Jan. 07) • BC1 Instrument package. (Jan. 07) • Toroids (in several locations) • BLM 11 (BLM 12 will be in) • Linac Access will be available to install these. • These are not on the Injector commissioning critical path.

  6. Injector Vault Installation Issues • Late: • The GTL support stand. • Will be here 11/16 • Laser table install, optics transport commissioning follows. • The Gun will be ready.

  7. Gun-to-Linac area Laser table To L0a Spectrometer GTL Gun GTL table

  8. Injector Vault Installation Issues • GTL beamline is late, now in machining. • Completion date is 2/8, we are pushing to advance this date and to stage delivery. • Stage delivery to advance laser vitual cathode commissioning, if possible. • This leads to a 2 month delay to e- commissioning. • January – February: • Laser commissioning • Controls checkout • RF processing of L0a and L0b • The 2007 commissioning goals will still be met.

  9. Commissioning Schedule 250 MeV 4.30 GeV 13.6 GeV 6 MeV 135 MeV Linac-0 Linac-X rf gun L0-a,b Linac-1 Linac-2 Linac-3 25-1a 30-8c 21-3b 24-6d ...existing linac 21-1 b,c,d undulator L =130 m X BC2 BC1 3/07 – 8/07 5/08 - 12/07- 4/08 SLAC linac tunnel research yard

More Related