1 / 8

National Environmental Policy Act

National Environmental Policy Act. Environmental Engineer US Army Garrison. NEPA. National Environmental Policy Act of 1969 US Army implementing regulation is AR 200-2. NEPA Requirements. Consider environmental impacts of proposed actions Evaluate alternative actions

saima
Télécharger la présentation

National Environmental Policy Act

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. National Environmental Policy Act Environmental Engineer US Army Garrison

  2. NEPA • National Environmental Policy Act of 1969 • US Army implementing regulation is AR 200-2 Environmental Quality Control Committee

  3. NEPA Requirements • Consider environmental impacts of proposed actions • Evaluate alternative actions • Disclose actions/impacts to the public • Integrate public participation into the decision making process Environmental Quality Control Committee

  4. NEPA ProcessDocumentation • Record of Environmental Consideration (REC) – 1 page, cost minimal • Environmental Assessment (EA) – 3-6 month process, cost $20K to $60K • FONSI • NOI • Environmental Impact Statement (EIS) – 1-5 year process, $200K to $Ms • ROD Environmental Quality Control Committee

  5. Public Notification? • REC – no • EA – yes • EIS – yes Environmental Quality Control Committee

  6. Project Proponents • Early integration of NEPA required • Responsible for funding NEPA documentation • Fully involved in NEPA process Environmental Quality Control Committee

  7. Recent NEPA Projects Allegheny Power Substation EA Fluoridation of the Drinking Water EA Commissary/PX/Fire Station EA NIAID EIS Installation EA Environmental Quality Control Committee

  8. Conclusion • NEPA is a legal and a US Army requirement • Project proponents must be fully involved • Call x3152 if you have any questions Environmental Quality Control Committee

More Related