An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CJLOTS 2013 Daily Synch – 11APR13

  2. Schedule – 12APR13 • Friday, 12APR13 • 0900 CUB Rehearsal • 1530 Daily Synch Brief

  3. Pier 9 OPNS ARFOR COP Pohang View 11 APR 13 II (+) 498 CSSB SBDE 501 X (-) II (+) Essential Node Legend Trident Pier OPNS Beach Head OPNS Pohang BOG Total ARFOR 555 Total JTF/Other 299 Total BOG 854 SIGACT: NSTR CCIRs Activated: FIR #7 IPDS/OPDS OPNS JRC Incheon Ssang Yong OPNS LAST 24 Hours 10APR JTF CDR arrives in Korea, JTF Temp TOC set-up 10APR DCO meeting by TF498 with Reserves on IPDS build 10APR Marshalling Yard ROC Drill 10APR Camp Carroll LOGPAC 10APR HSV ISO IIIMEF arrives 10APR Barber Shop opens on the LSA I (-) Marshall Yard OPNS JRC Gimhae NEXT 24-48 Hours 11APR LSV 4 arrives from Hawaii 11APR 2x LCU 2000’s arrived from Japan 11APR Combined Convoy with ROK for CL I resupply to Busan 12APR Laundry, Galley, Barber Shop operational at LSA 12APR Camp Carroll LOGPAC 12-13APR Duck Pond Build (D7 Dozer) 10 551 Marshalling Yard/DLA Yard LSA OPNS ARFOR Reception LSA ICTC • COMMANDERS COMMENTS:

  4. NBG 1 Update – 11APR13 Next 24 Hours • Last 24 Hours • -Continued fabrication of decking.- Continued establishment of C2 nodes & supporting facilities at the beach and pier.  (Facilities at Dogu Beach include:  JLCC, J-Staff admin tent, NSE comms tent & SIPR tent.  Facilities at the pier include:  Lighterage Support Center (LSC), Lighterage Repair Facility (LRF), Battalion Aid Station (BAS) (medical), Underwater Construction Team (UCT) admin/ops tent, and warming tent.)- Held additional meetings with Army & Marine counterparts to discuss the flow of cargo at the beach and beach space management.- Received NSE main body (143 total personnel from PHIBCB ONE (114), ACU-1 (17), UCT TWO (7) & NBG-1 (4)) tonight. • Continue work at beach & pier C2 nodes and supporting facilities. • Participate in additional coordination meetings as required for beach throughput and space management. • Prepare for opening of galley, laundry & barber services. Comments/Concerns 190 NSE personnel currently on board the LSA

  5. Daily Status Report • -Staff continues to gather; Coast Guard, ROK, 501st LNOs have reported in and begun operations.  CNFK observers are on station. • -Conducted JOC leveling/Conops brief with watchstanders and MSC personnel. • -LSV arrival is expected at 0200L this evening (4 hours later than projected).  • -2 LCU's arrived as expected this afternoon. • -Continued coordination of beach area to support layout of IPDS has not produced a solution yet. 

  6. Work in Progress -Retrograde Planning (CDR Sumagaysay) -CUB Shell (LTJG Weston / CPT Gerlach) -ISDN Listing (MSgt Lawson) -Night Order Shell (OS2 Bryant) -AAR Tracking/Reporting (CDR Freeman)

  7. POC CUB Collators: -ABWC: LTJG Jill Weston -ABWC: CPT Eddie Gerlach -ABWC: LT Rob Mack

  8. Requirements • -