1 / 105

Asphalt Roadway

Asphalt Roadway. Daily Report of Quality Control (Form No. 675-030-20). A step by step guide. This is calculated from the Gmm on the Mix Design. It is Gmm times 43.3 times thickness of the lift. Automatic Calculation. Automatic Calculation. Automatic Calc. If within tolerance, # is Blue,

shae
Télécharger la présentation

Asphalt Roadway

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Asphalt Roadway Daily Report of Quality Control (Form No. 675-030-20) A step by step guide

  2. This is calculated from the Gmm on the Mix Design. It is Gmm times 43.3 times thickness of the lift.

  3. Automatic Calculation

  4. Automatic Calculation

  5. Automatic Calc. If within tolerance, # is Blue, if not # is Red

  6. New sublot MUST be started on separate line

  7. Automatic Calculation

  8. Automatic Calculation

  9. If spread is within the allowable tolerance, # is Blue, if not # is Red. If out tell Foreman and document it in the Remarks at the bottom of the page.

  10. Proper number and correct spacing is VERY important!

  11. Enter previous tons, Sq. Yards & Tons in This Lot

  12. These daily totals go here Automatic calculation

  13. Input the waste from the days production Automatic calculation

  14. These Tonnages Are Totals for This Pay Item

  15. Density Required Previous Tonnage: Today’s Tonnage: Total Density Required:

  16. No Density Required Previous Tonnage: Today’s Tonnage: No Density Required Total Tonnage:

  17. These 2 numbers must equal this one: These 3 numbers must equal this one:

  18. Compaction Temperature from Mix Design

  19. Avg. of all temperatures, Max. temp of the day, Min. temp. of the day & Avg. temp of the 1st 5 loads.

  20. Enter pay item for tack. If tack is included in the price of the asphalt, enter the pay item for the type of asphalt being placed. Prime calculations can be entered here if prime is being used

  21. Enter the type of tack being used.

  22. Enter the distributor number (FDOT calibration number) that is being used to place the tack. (From previous slide)

  23. Look up beginning depth reading and the corresponding gallon reading

  24. Enter the beginning measurement and the corresponding gallons from the tack chart. REMEMBER: NO CHART~NO START

  25. Look up ending depth reading and the corresponding gallon reading

  26. Enter the ending measurement and the corresponding gallons from the tack chart after tack is shot. This is an automatic calculation. (Beginning gallons minus ending gallons.)

  27. Enter the time you finished shooting the tack and the temperature of the tack from the distributor.

  28. Look up temp. on chart and select corresponding Correction Factor.

  29. Enter the correction factor for the temperature of the tack.