THEMIS Mission Integration Working Group (MIWG) #7 Ground Operations Working Group (GOWG) #5

THEMIS Mission Integration Working Group (MIWG) #7 Ground Operations Working Group (GOWG) #5 Delta - Ground Operations Review (GOR). November 29, 2006 KARS Park, KSC, Florida Hosts: Garrett Skrobot, NASA Mission Manager (MM)

shania
Télécharger la présentation

THEMIS Mission Integration Working Group (MIWG) #7 Ground Operations Working Group (GOWG) #5

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. THEMISMission Integration Working Group (MIWG) #7 Ground Operations Working Group (GOWG) #5 Delta - Ground Operations Review (GOR) November 29, 2006 KARS Park, KSC, Florida Hosts: Garrett Skrobot, NASA Mission Manager (MM) William Van Dyke, NASA Launch Site Integration Manager (LSIM)

  2. AgendaNovember 29, 2006 Meet-Me-Number: 1-877-991-5876  Passcode: 698067# MISSION INTEGRATION WORKING GROUP (MIWG) #7 • THEMIS Project Status P. Harvey/UCB • Payload Schedule Update (Astrotech and Launch Site Schedules) • Delta Program Status L. Loucks/Boeing • LV Hardware Status • Program Issues • Mission Integration Status L. Loucks/Boeing • Integration Schedule • Requirements Verification Matrix D. Tran/Boeing • SCN Review • Release of ICD Rev A • Action Item Review • Launch Site Integration Status • Side by Side Testing/Ladder Mods/SSS Installation V. Segall/Boeing • Fueling & Procedure Status C. Davis/NASA • Range Status on Required Deliverables & Procedures J. Wethern/45SW

  3. AgendaNovember 29, 2006 Meet-Me-Number: 1-877-991-5876  Passcode: 698067# MISSION INTEGRATION WORKING GROUP (MIWG) #7 - Continued • Analysis Results L. Loucks/Boeing DTO Update • Thermal • RF Link Analysis • Controls/ACS Gas Budget Update • Mobile Telemetry Coverage L. Loucks/Boeing • Launch Management Update KSC • Mission Success Overview KSC • Review Spacecraft Mandatory / Required Launch Criteria KSC

  4. AgendaNovember 29, 2006Meet-Me-Number: 1-877-991-5876  Passcode: 698067# GROUND OPERATIONS WORKING GROUP (GOWG) #5/ Delta GOR • Astrotech Readiness/Issues G. Gleeson/ASO FL • THEMIS Badging & Training Plan K. Kerr/Analex KSC • Launch Site Safety Status/Readiness C. Loftin/NASA Safety • Telemetry and Communications Status/Readiness M. Lougheed/NASA KSC • Spacecraft Procedure Status/Review R. Sterling/UCB • Launch Site Readiness Poll (Go/No Go) • THEMIS Project P. Harvey • NASA KSC Public Affairs G. Diller • Boeing Delta Mission Integration V. Segall • Astrotech Mission Management G. Gleeson • NASA LS Telemetry & Communicaitons M. Lougheed • NASA KSC Safety C. Loftin • NASA MM G. Skrobot • NASA LS Launch Site Integration W. Van Dyke • NASA LS Launch Site Integration Branch F. Stone

  5. THEMIS PAYLOAD STATUS Peter R. Harvey Project Manager University of California - Berkeley

  6. Payload Status • PCA Assembly and Test

  7. Payload Status Acoustics & Shock Vibration Spin Balance Thermal Vacuum FM2/FM3 Thermal Vacuum Storage

  8. ASO/PAD Schedule 1

  9. ASO/PAD Schedule 2 Note: RCS MEOP & Leak are performed after hours

  10. ASO/PAD Schedule 3

  11. ASO/PAD Schedule 4

  12. ASO/PAD Schedule 5

  13. ASO/PAD Schedule 6

  14. ASO/PAD Manpower Manpower • 27 Max while at ASO • 31 Max while at PAD

  15. Summary Summary Status • Probes and Probe Carrier are Flight Ready • Plans and Procedures for ASO/PAD in Good Shape • Shipment Contracted Two Trucks w/ Lead Car Ready Issues Potentially Impeding Launch Processing • None

  16. Side by Side Testing / Ladder Mods / SSS Installations V. Segall / Boeing KSC

  17. Cape Status • Access Ladder • Ladder modified, proof loaded, available for use • Side-by-Side Testing • Procedure written and reviewed; ready for use • Date (15 Dec) coordinated • Logistics of delivery (14 Dec) discussed • Fork lift identified and available • Mission Integration will facilitate access for non-badged people • Actual delivery schedule discussion planned for post Astrotech THEMIS delivery

  18. Cape Status • SSS Installation • Installation will be at Astrotech • Task is a payload support function; not a liability issue • Procedure (DCI) is written and in the review process • Date is under review: THEMIS requests the week of 18 Dec, but Boeing may not be ready until after the 3rd of Jan. See schedule • Later date needs real time coordination in parallel with THEMIS fueling activities in the HPF • The SSS installation is planned for a separate bay so that mechanical operations will be de-conflicted

  19. KSC Fueling Team Status for THEMIS Presented to: THEMIS Pre-Ship GOR By: Chuck Davis Fueling Team Lead, TA-E3 November 29, 2006 KSC

  20. KSC Fueling Team Status • Procedures: • THEMIS-specific deviations to OMI’s E5534 & E5502 are complete & under final review prior to obtaining signatures • OMI E5535 off-load procedure & pre-planned THEMIS-specific deviations will be available if required • ICD “Appx. C” is complete • MSPSP - Fueling GSE portion is complete • All GSE will be in-calibration at the time of use • Schedule: • Mobilize to Astrotech and set up GSE week of Dec 11 • Connect to spacecraft ~ Jan 3 • Prop load Jan 4 • Prop Loading Team is GO for THEMIS shipment

  21. Range Status on Required Deliverables & Procedures J. Wethern/45SW

  22. Range & Deliverables Status • MSPSP RELEASED & APPROVED • All required deliverables are up to date • PC handling procedure & Side by Side test are in review • All hazardous procedures in the NPF require Range Safety approval

  23. Astrotech Readiness / Issues Gerard Gleeson / ASO FL

  24. Mission Specific Items • Item 1005 Phone installation in Control Room – to be performed after arrival, units available • Item 1030 Training and Badging - to be performed after arrival • Item 1101 SCAPE Suits – to be delivered as required prior to loading operations • Item 1180 Training for Cranes and Forklifts - to be performed after arrival • Item 4000 LAN configuration – to be completed on arrival – infrastructure is ready • Item 4110 IONet configuration – to be completed on arrival – infrastructure is ready • Item4500 Voice Stations - to be installed after arrival, units available • Documentation • UCB Procedures received and reviewed, Comments sent to UCB • No major issues associated with Themis processing at Astrotech • Deliverables • All deliverables on site and ready for use, certificates presented in Data package as required Astrotech is ready to receive THEMIS

  25. ASO Occupancy

  26. THEMIS Badging & Training Kathy Kerr / Analex KSC

  27. KSC Badging & Training Status • SLC-17 Badging & Training • 41 THEMIS personnel identified for unescorted access to SLC-17 • 36 have good NAC/PRP; 5 are In Process • 5 THEMIS personnel identified for SCAPE operations. • 4 have completed SCAPE training; 1 person remaining • Open items: • Required training: ELSA, CCAFS Safety and SLC-17 walk downs to be scheduled post spacecraft arrival. • Schedule SCAPE training for one remaining person • AF Form 2856s have been completed and submitted to me. They will be submitted to Pass & ID about 1 month prior to required pad access. • Air Force Badging once prerequisites have been completed. • Launch Site Planning Readiness Statement: • Plans are in place to complete remaining open items. • KSC Badging & Training is ready for THEMIS flight hardware arrival.

  28. NASA / KSC Safety Readiness for THEMIS Chuck Loftin System Safety Engineer KSC Safety & Mission Assurance Launch Services Division 29 November 2006

  29. Safety Documentation Status • MSPSP - Final MSPSP approved 2 Nov 06 • S/C Processing - Ground Processing Approval letter provided prior to THEMIS Delta GOR • Procedures - Integrated and Contingency Procedures under review

  30. Readiness Statement • NASA/KSC Safety and Mission Assurance, Launch Services Division has assessed the readiness of the THEMIS spacecraft for NASA at Astrotech, and has no constraints to the arrival of the Spacecraft. - Any open items or issues are being tracked via the Verification Tracking Log (VTL).

  31. Telemetry and Communications Status / Readiness Marty Lougheed / NASA KSC

  32. TELEMETRY & COMMUNICATIONS READINESS • NASA Communications has had no change in our position since the THEMIS GOR …………… • we are "GO" for the THEMIS 11 Dec arrival.

  33. Status of Launch Site Procedures Rick Sterling Themis I & T Manager

  34. Launch Site Procedures Following charts show status, where used and whether hazardous.

  35. Launch Site Procedures To download procedures or see more detailed listing including author, revision number, etc: ftp://apollo.ssl.berkeley.edu/pub/THEMIS/2 Space Segment/2.2 Spacecraft/2.2.7 Launch Site Processing/2.2.7.1 Launch Vehicle Integration

  36. Launch Site Readiness Poll William Van Dyke / NASA KSC

  37. Launch Site Readiness Poll (Go/No Go) • THEMIS Project Peter Harvey • NASA KSC Public Affairs George Diller • Boeing Delta Mission Integration Vic Segall • Astrotech Mission Management Gerard Gleeson • NASA LS Telemetry & Communicaitons Marty Lougheed • NASA KSC Safety Chuck Loftin • NASA MM Garrett Skrobot • NASA LS Launch Site Integration William Van Dyke • NASA LS Launch Site Integration Branch Frank Stone