1 / 17

CUBS SGM2, May 13, 2004

CUBS SGM2, May 13, 2004. Matti Hämäläinen Centre for Wireless Communications University of Oulu, Finland matti.hamalainen@ee.oulu.fi. Contents. Opening Approval of the agenda Minutes of the last meeting Summary of fulfilled work amounts and costs Revision of the research plan

shaun
Télécharger la présentation

CUBS SGM2, May 13, 2004

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CUBS SGM2, May 13, 2004 Matti Hämäläinen Centre for Wireless Communications University of Oulu, Finland matti.hamalainen@ee.oulu.fi

  2. Contents • Opening • Approval of the agenda • Minutes of the last meeting • Summary of fulfilled work amounts and costs • Revision of the research plan • Contract status • Summary of CWC’s new UWB activities • Other business • Next meeting • Closing CUBS, the 2nd steering group meeting

  3. Minutes of the last meeting • Kick-off: January 27, 2004, 9.15-12.00 • Open items: • update to research plan • done • PHY-simulator has been offered to IEEE802.15 • no interests anymore • biased to multiband approach • no expected simulator release CUBS, the 2nd steering group meeting

  4. Summary of fulfilled work amounts and costs • Work amount from April (4.53 mm) CUBS, the 2nd steering group meeting

  5. Work: 1.1. – 30.4.2004 CUBS, the 2nd steering group meeting

  6. Cum. work: 1.1. – 30.4.2004 CUBS, the 2nd steering group meeting

  7. CUBS, the 2nd steering group meeting

  8. Results from the first third • WP1: Multiband UWB • literature survey has been started • WP2: Singleband UWB • office (Tietotalo) • channel models ready • outdoors (Riihimäki) • channel models ready • link level simulations almost ready • industry (Stora Enso) • data analysis has not been started yet • multiband interference + MAI simulations in SV-channel • first results available CUBS, the 2nd steering group meeting

  9. WP3: Sensor networks • Niina’s work gives the first estimates for PHY to be used • Energy efficient channel codes for sensor networks • WP4: Co-existence • UWB impact on WCDMA and GSM have been measured in co-operation with PULSERS-project • UMTS • GSM900, GSM1800 • WP5: Capacity • work has been started • analytical work will be done in Finnish Academy project (CASWI) • results will be reported to CUBS CUBS, the 2nd steering group meeting

  10. WP6: Channel measurements • summer trainee has joined the project • modification to the measurement system • VNA -> SPA in long range freq. domain sounder • proposal to Oulu University Hospital has been sent • first response was optimistic • on May 25, JI and MH will visit the hospital presenting our ideas and sounding systems • outdoors • first discussions with Heikki CUBS, the 2nd steering group meeting

  11. Costs from 1.1. – 30.4.2004 CUBS, the 2nd steering group meeting

  12. Outputs • Licentiate thesis accepted May 5, 2004 (Raffaello) • two M.Sc. thesis will be finished at June 2004 (Lassi, Niina) • one paper accepted to IWWAN • H. Karvonen, Z. Shelby ja C. Pomalaza-Raez: Coding for Energy Efficient Wireless Embedded Networks • three papers have been submitted to NRS • H. Karvonen, C. Pomalaza-Raez: Coding for Energy Efficient Multihop Wireless Sensor Networks • N. Laine, M. Hämäläinen, L. Hentilä, J. Iinatti, M. Nenonen, S. Karhu: Outdoor Ultra wideband radio channel modeling at VHF/UHF band • L. Hentilä, V. Hovinen, M. Hämäläinen: Sub-band analysis in UWB channel modeling • two papers will be presented in IWUWBS&UWBST next week (from FUBS) • M. Hämäläinen, R. Tesi, J. Iinatti: UWB Co-Existence with IEEE802.11a and UMTS in Modified Saleh-Valenzuela Channel • R. Tesi, M. Hämäläinen, J. Iinatti, I. Oppermann, V. Hovinen: On the Multi-User Interference Study for Ultra Wideband Communication Systems in AWGN and Modified Saleh-Valenzuela Channel CUBS, the 2nd steering group meeting

  13. Work deviation • Work amount in WP2 has been exceeded • analysis of industrial channel data not started • PHY simulations using own channel models are needed • Reaction: • WP1: MB-OFDM (13) • 3 mm -> WP2 • WP4: co-existence (7) • measurement work with EU-projects • 1 mm -> WP2 • WP5: capacity (5) • analytical work to be done in CASWI • 2 mm -> WP2 Increase 6 mm to WP2: 11 -> 17 mm CUBS, the 2nd steering group meeting

  14. Revision of the research plan • Updated plan • has been accepted via email discussion • commenting time ends at Feb 11, 2004 • no arguments against the updates were presented • has been available at CUBS web-page since Feb 11, 2004 • WP6: Channel modelling added to the plan, amount 6 mm. • hospital • request to hospital has been sent • supplementary outdoor measurements. • discussion started with Heikki • summer trainee available (May – Aug) CUBS, the 2nd steering group meeting

  15. Contract status • Comments from Elektrobit has been taken into account • UO has reviewed the comments • contract draft is updated and it is available at the CUBS web-page CUBS, the 2nd steering group meeting

  16. Summary of CWC’s new UWB activities • UWB-hospital (UHo) – application submitted • Tekes FINWELL-program • feasibility study: UWB in hospital • sponsor: Innocas Medical • WIreLess Technology in Hospital Operation management (WILHO) – application submitted • Tekes FINWELL-program • UWB in hospital • sponsors: Innocas Medical, Oulun diakonissalaitos, Ekahau, Yomi, Pfizer • Multi Mode Match Analysis (M3A) – application submitted • Tekes Phoenix-program • sponsors: Nokia, Polar Elektro • co-operation: Media Team, Kilpa- ja huippu-urheilun keskus CUBS, the 2nd steering group meeting

  17. Other business • Next meeting • TSG: June 9 • SGM: CUBS, the 2nd steering group meeting

More Related