Controls Overview April 27, 2005

Controls Overview April 27, 2005. Outline Goals Status update Resources Design Slides for Global Systems Task descriptions Next 6 months Conclusions Note: As this is being recorded – please add ” it is my impression” and “we expect “ wherever appropriate. LCLS Control System Goals.

shelleyh
Télécharger la présentation

Controls Overview April 27, 2005

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Controls OverviewApril 27, 2005 • Outline • Goals • Status update • Resources • Design Slides for Global Systems • Task descriptions • Next 6 months • Conclusions • Note: As this is being recorded – please add ” it is my impression” and “we expect “ wherever appropriate.

  2. LCLS Control System Goals • Provide a fully integrated control system to support the construction, test, installation, integration, operation and automation of the LCLS Accelerator • Standardize on all devices and components across all subsystems. • Identify all data either by pulse id, beam pulse related time stamp, or 500 msec rough time stamp. • Full integration with the SLC – timing, use of LCLS data in SLC high level applications, and use of SLC data in LCL • Provide an upgrade path for the SLC

  3. Update May 2004 – April 2005 (1) • 3 month continuing resolution • WBS reorganized to move all design work into 1.1.3.5 under direction of the control group • Acquire personnel • 8 project engineers – Koturri, Lucchini, Allison, Straumann, Murray, Fairley, Rogind, (offers being made to junior engineer, jobs open for junior proj. eng) • 1 low level programmer (offer being made to junior engineer) • 2 EE/ board designers – (support from ESD, evaluating existing designs, interviewing • Steve Lewis on controls at LLNL • Conventional Facilities, Wiring, Racks, and Power Distribution – Ortega (lead), ESD support, need to hire

  4. Update May 2004 – April 2005 (2) • Facility Controls, XRay Transport are integrated into control design (details remain) • Rack Layout, Tray Design, and wiring penetrations for Injector, L01 through BC1. LTU is 50% complete. • Prototypes in test: • PNet – hardware design complete, driver functional, tests needed • Timing – hardware from SLS being put into test • Power Supply – hardware from SLS in test for stability and precision • Video – cameras in test • SLC-Aware IOC is 70% complete.

  5. Update May 2004 – April 2005 (3) • Design efforts ready for prototyping: LLRF and BPM • Prototypes needed • 120 Hz fast feedback • position controllers • Machine Protection

  6. Personnel – Resources Ctl. Elec. Engineer Ctl. Sr. Elec. Tech. Ctl. Elec Tech. Pwr. Elec. Engineer Pwr. Sr. Elec. Tech. Control Prog. 2004 2.42 .56 .07 1.94 .42 .81 2005 10.37 3.44 .60 1.39 .86 10.18 2006 8.12 2.66 2.20 .32 .31 10.29 2007 6.07 1.90 4.63 .51 .72 6.32 2008 3.26 .77 .62 .10 .05 6.56 Total 30.24 9.33 8.12 4.26 2.37 34.17 Ramp up plan: offset 3 months. We are borrowing most of our hardware support. We need some LCLS in-house support Will be reworked after hardware designs are reviewed and finalized.

  7. Integration with the SLC Control System EPICS W/S Distributed Applications SLC Alpha All High Level Apps EPICS W/S Distributed Applications EPICS W/S Distributed Applications Xterm Xterm Xterm EPICS W/S Distributed Applications Xterm EPICS WS Distributed High Level Applications SLC Net (Data Communication) KISNet (fast closed loop control data) PNet (Pulse ID / User ID) MPG Ethernet (EPICS Protocol) micro Micro emulator I/OC (SLC-aware) EVG Camac I/O RF reference clock

  8. SLC-Aware IOC

  9. System Design EPICS W/S Distributed Applications EPICS W/S Distributed Applications SLC Alpha Apps EPICS W/S Distributed Applications Xterm Xterm EPICS W/S Distributed Applications Xterm EPICS WS Distributed High Level Applications Xterm Fast Feedback over Ethernet? SLC-Net over Ethernet Channel Access Vacuum Ctrl EVR Pwr Supply Ctrl C P U E VG EVR LLRF EVR Diag C P U HPRF I/O Boards C P U C P U IOC IOC IOC 16 triggers 16 triggers Single Bunch Beam Dumper Drive Laser Off Machine Protection Beam Code + EPICS Time + EPICS Events

  10. LCLS Project Engineering Tasks • 1 RF Control - Koturri • 3 Diagnostics – Straumann, Murray, tbd Toroids & Faraday Cups, Beam Stops, Profile Monitors & Video Devices, Wire, Scanners, Bunch Length Monitors & E/O Diagnostics, Beam Position Monitors, Collimators, All other stops • Gun Laser and Drive Control – Contract Out • 1 Vacuum – Steve Lewis supporting the design now / Job Ad Open • 1 Magnet Power Supply Control IOC and software - Luchini • 1 Beam Containment / Personnel Protection / Machine Protection - Chevstov • 1 Low Level Engineer - Norum • 2 High Level Application Engineers – Fairley, Rogind • 1 RDB Manager – job ad placed • 1 System manager – need to place job ad • Resolve/Formalize Group Leader – currently co-managed Bob and Patrick

  11. LCLS Software Tasks – Purchase/Steal/Develop • SLC-aware IOC – 70% complete. Expected completion July 1, 2005. • Machine Protection / Mitigation (look at SNS and JLAB) • Master pattern generator (look at PSI/Diamond) – being set up • Fast Feedback Communication – need to prototype • High Level Applications (Matlab or XAL) • Correlation Plots (look at JLab) • Fast Feedback Loops • Emittance reconstruction from wire scans and profile monitors • Profile monitor image analysis for slice emittance with the transverse cavity • Beam Steering and online orbit modeling • Beam Steering “scans” to emittance reconstruction from wire scans and profile monitors

  12. LCLS Software Tasks – Purchase/Steal/Develop • Data Archiving to support all phases of the project (SNS) • Operator Display Tools / Synoptic, Plots, Waveform, Image (EDM) • Alarm Management (ALH, CMLOG) • Electronic Log (DESY, JLAB) • High Level Application Support: Matlab, XAL, Python • Control System Configuration Tools (VDCT, RDB) • Relational Database Management in all project aspects (Based on SNS, PEP) • Naming Standard (PEP)

  13. LCLS Hardware Tasks – Purchase/Steal/Develop (1) • Global • New timing boards – Master Pattern Generator and Event Receiver Boards (PSI,DIAMOND) • Machine Protection System (SNS/JLAB) – needs to be evaluated • RF Control – In-house analog with COTS ADCs and DACs • Diagnostics • Toroids & Faraday Cups • Beam Stops • Profile Monitors & Video Devices – evaluating commercial cameras • Wire Scanners • Bunch Length Monitors & E/O Diagnostics • Beam Position Monitors – in-house analog with COTS ADCs and DACs • Collimators • All other stops

  14. LCLS Hardware Tasks – Purchase/Steal/Develop (2) • Gun Laser and Drive Control – Integrate Thales Controls either device layer or Labview • Vacuum Standards – being finalized • Magnet Power Supply Controllers (PSI) – in test at SLAC • Beam Containment / Personnel Protection – through first review

  15. Next 6 months • Finish hiring: • hardware support – EEs and Techs • Complete hiring actions on project engineers and programmers. • Acquire RDB support. • Complete detailed designs per subsystem and have them reviewed – revamp costs – by the end of this FY. • Complete evaluation/test of PNet, Timing, LLRF, PS, MPS, PPS, and BPM • Complete the SLC-Aware IOC • Integrate Laser Control

  16. Conclusions • Control engineers are in place for most major subsystems. • The WBS has been reorganized to move all of the design activities into global controls under 1.1.3.5. Signature authority for all x.x.2 level WBS is shared. • The SLC-aware IOC and SLC to EPICS timing issues are well on the way to being resolved. • Hardware components have been identified for most of the risky areas. MPS and fast feedback need attention. PPS needs to complete the citizen review. • By the end of this year, hardware designs should be proven as prototypes and the schedule and budget revamped to reflect the final design decisions.

  17. Timing Nsec resolution on the timing gates produced from the Event Rcvr 20 psec jitter pulse to pulse Event generator passes along beam code data from SLC Event generator sends events to receivers including: 360 Hz, 120 Hz, 10 Hz and 1 Hz fiducials last beam pulse OK Machine mode EPICS time stamp Event receivers produce to the IOC interrupts on events data from the event generator in registers 16 triggers with configurable delay and width 476 MHz RF Reference SLC micro Master Pattern Generator 128 bit beam code @ 360 Hz FIDO 119 MHz w/ 360 Hz fiducial Vacuum Ctrl EVR Power Supply Ctrl C P U E VG EVR LLRF EVR Diag C P U HPRF I/O Boards C P U C P U IOC IOC IOC 16 triggers 16 triggers Single Bunch Beam Dumper Drive Laser Off Machine Protection Beam Code + EPICS Time + EPICS Events

  18. SLC Net “Micro” Communication Provides data to SLC Applications from EPICS Operates at 10 Hz (not beam synched) Requires significant development in the IOC to emulate SLC “micro” in the IOC On an application by application basis we will evaluate what functions to provide SLC Alpha Apps Xterm Xterm Xterm Xterm SLC-Net over Ethernet Vacuum Ctrl EVR Pwr Supply Ctrl C P U E VG EVR LLRF EVR Diag C P U HPRF I/O Boards C P U C P U IOC IOC IOC

  19. Channel Access EPICS W/S Distributed Applications EPICS W/S Distributed Applications SLC Alpha Apps EPICS W/S Distributed Applications Xterm Xterm EPICS W/S Distributed Applications Xterm EPICS WS Distributed High Level Applications Xterm Channel Access Vacuum Ctrl EVR Power Supply Ctrl C P U E VG EVR LLRF EVR Diag C P U HPRF I/O Boards C P U C P U IOC IOC IOC A channel access server in SLC provides data from existing SLC micros to EPICS applications All IOCs have both a channel access server to allow access and a client to have access Channel access provides read/write by all clients to all data with a server. All EPICS high level applications are channel access clients that may or may not have a server.

  20. Fast Feedback Fast feedback is required to run at 120 Hz Values will be transmitted from RF and selected diagnostics to Power Supply and RF IOCs The communication needs to be reliable, verifiable, and have a well thought out degradation The entire time budget to read, transmit, commute, control, and settle is 8.3 msec First estimates are that the control system can use 2 msecs to transmit and receive the data Can this be done over a common Ethernet with adequate bandwidth – or is a dedicated one needed? Fast Feedback over Ethernet? Vacuum Ctrl EVR Power Supply Ctrl C P U E VG EVR LLRF EVR Diag C P U HPRF I/O Boards C P U C P U IOC IOC IOC

  21. Machine Protection Machine protection is used here to define faults requiring global mitigation Response time is under 8 msec There are two mitigation devices: Single Beam Dumper - which prohibits the beam from entering the undulator Drive Laser Off – which prohibits beam from entering the cavity Action must also be taken to reduce the repetition rate of the beam This new design is required to interrupt the beam before the next beam pulse. Vacuum Ctrl EVR Par Supply Ctrl C P U E VG EVR LLRF EVR Diag C P U HPRF I/O Boards C P U C P U IOC IOC IOC Single Beam Dumper Drive Laser Off Machine Protection