SlideServe
Menu
Préférences
© SlideServe · v2026

Power Supply System Impacts

shen avatar
4 diapositives · 216 Views · Sep 01, 2014

Power Supply System Impacts. WBS 1.1.3 Power Supply System Level 3 Manager Nancy Grossman FNAL Dec 11, 2001. Update of PS Needs. V109 has one more 6-3-120 (now 4 instead of 3) and runs at a higher current (1050 amps) Requires another 500 KW supply to get the needed volts.

Power Supply System Impacts - slide 1
01 / 4Power Supply System Impacts
1 / 17

Télécharger la présentation

Power Supply System Impacts
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Power Supply System Impacts WBS 1.1.3 Power Supply System Level 3 Manager Nancy Grossman FNAL Dec 11, 2001

  2. Update of PS Needs • V109 has one more 6-3-120 (now 4 instead of 3) and runs at a higher current (1050 amps) • Requires another 500 KW supply to get the needed volts. • Have space for 1 more 500 KW in TSB. • Only remaining 500 KW PS are old Transrex’s, we are checking on getting an additional one (or other options, and checking the ramp). • V110 has one less EPB (now 5 instead of 6) and runs at a higher current (1400 amps) • Does not require an PS changes, will need to re-calculate the ramp. • Q109 is now two different quads (3Q120, 3Q60) which can run on one supply. • Two possible 3Q120’s (quads) in the carrier tunnel (unlined region) • Will need an additional PS each (there is room for them and we have spares) • Cable lengths and costs all need to be re-estimated.

  3. Update of Regulation Needs • Magnet Strings regulation requirements are looser with the new beam optics. • Could use less regulation than we have budgeted for, if this remains true. • Not clear if loosening the regulation is worth the money saved. • Don’t need to decide until FY2003. • Costed filters for all 7 strings, and BmLB systems for 3 strings, HOLEC transductors and special FNAL electronics for all 7 strings.

  4. Summary All these comments are very preliminary and Steve Hays will check in detail to see what are the final implications. • Main Changes: • Need extra 500 KW for V109. • Need 2 more quad PS if put quads in carrier tunnel. • PS regulation requirements are looser. • Cable lengths and numbers. • (need to re-do ramp calculations and cable calculations/costs) • Implications: • Can we get additional cable (500 kcm) or is it too late? Not sure if we will need it or not… • Additional costs are for 500 KW PS and quads and cables. Estimate several ten’s of thousands of dollars (FY$98). • Might be able to save money on PS regulation, but we would need to think long and hard before doing that.