An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mike MrazChairman, PWG RBC Field Trial – Chief Dispatchers February, 15, 2011 Webinar

  2. Welcome - Purpose • Why we’re here • Who’s talking about what when • What haven’t we answered • What do we do to follow up

  3. Agenda - Presenters • Background and Field Trial Process – Mike Mraz • RC and BA Roles – Mike Mraz, Robert Williams • Interconnection Field Trial performance – Anitha Neve

  4. RBC Background & Review • BAL-007- BAL-011 (draft) • Establish technically defensible standards to maintain interconnection frequency within predefined frequency limits, prevent frequency instability, and unplanned tripping of load or generation • Identify roles and responsibilities of BA and RC • Establish methodology for establishing interconnection frequency limits

  5. RBC Review continued • CPS1 kept intact • Balancing Authority ACE Limit • Based in part on cascading limit sets: • Frequency Relay Limits (High, Low) • Frequency Abnormal Limits (High, Low) Frequency Trigger Limits (High, Low)

  6. RBC Review continued • Replacement for CPS2 • Frequency based ACE limits using 1-min clock averages: • For FA < 60 Hz BAALLow = (-10BI(FTLLOW-60)2/(FA-60)) • For FA > 60 Hz BAALHigh = (-10BI(FTLHigh-60)2/(FA-60)) • For FA = 60, BAAL = 0 • FTLLow = 59.932, FTLHigh = 60.068 • BA’s have 30 minutes to return ACE to within Limits

  7. Field Trial process • Duration • 1 year with annual renewal on OC approval • Currently approved through Feb 2012 • WECC proposed an additional limit • Intended to address transmission concerns from “opposing ACE” values • ACE Transmission Limit (ATL) • Initially set at 2*L10, now 4*L10 • Set at discretion of PWG • 30 min return criteria applies

  8. Field Trial Process continued • BA Participation • All BAs recommended • CPS2 waiver granted for participants • 25 BAs currently participating • AGC changes not req’d but “relaxation” is recommended • Data is collected, analyzed and discussed monthly by PWG and SDT

  9. BA & RC Responsibilities • BA Responsibilities • Operate to BAAL/ATL criteria • Calculate BAAL, ATL • Identify and inform operators of exceedances • Train operators on RBC and FT • Send BAAL, ATL limits to RC • Collect monthly data as specified in FT document • Report on circumstances where ACE > BAAL or ATL > 20 min, 30 min

  10. BA & RC Responsibilities – cont’d • RC Responsibilities • Laid out in FT document • Drawn from draft BAL-008 • Monitor BAs for ACE exceeding BAAL, ATL • Request BAs to return ACE within limit • Other actions as appropriate for FAL and FRL

  11. Field Trial resources • WECC - PWG • Field Trial document, approved by OC • Workshop materials • Field Trial Data archival (restricted) • NERC Project 2010-14 – Balancing Authority Reliability-based Control

  12. Questions?