1 / 13

Dr. Gamani Chandrasena Vice Chancellor Uva Wellassa University, Sri Lanka

Dr. Gamani Chandrasena Vice Chancellor Uva Wellassa University, Sri Lanka. Progress Review On Ongoing Construction Projects a imed at Budget - 2016. Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri Lanka.

spengler
Télécharger la présentation

Dr. Gamani Chandrasena Vice Chancellor Uva Wellassa University, Sri Lanka

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Dr. GamaniChandrasenaVice ChancellorUva Wellassa University, Sri Lanka Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri Lanka

  2. Construction (Capital) Projects of Uva Wellassa • Phase I • Phase II Phase I • Administration Building Block • Lecture Hall + Lab (Block A) • Lecture Hall + Lab (Block B) • Lecture Hall + Lab (Block C) Total Cost Estimated (Amended TCE) => Rs. 350 Million Actual Expenditure incurred to 30.06.2015 => Rs. 348 Million Future Commitment (Final Bill to be Settled) => Rs 10 Million Physical Process : 100% Financial Progress : 99% • Administration Building Block • Awarding On : 03rd Aug 2005 • Completed On : 16th Oct 2006 25 August 2015

  3. Lecture Hall + Lab (Block A) • Awarding On : 03rd Aug 2005 • Completed On : 01st Nov 2006 • Lecture Hall + Lab (Block B) • Awarding On : 03rd Aug 2005 • Completed On : 11th Oct 2006 • Lecture Hall + Lab (Block C) • Awarding On : 03rd Aug 2005 • Completed On : 11th Oct 2006 25 August 2015

  4. Phase II • Hostel Block No. 1 • Awarding On : 01st Jul 2006 • Completed On : 30th Jul 2007 • Physical Progress : 100% • Financial Progress : 87% • Hostel Block No. 2 • Awarding On : 01st Sep 2006 • Completed On : 26 Jun 2008 • Physical Progress : 100% • Financial Progress : 87% • Hostel Block No. 3 • Awarding On : 01st Aug 2006 • Completed On : 04th Dec 2008 • Physical Progress : 100% • Financial Progress : 87% 25 August 2015

  5. Hostel Block No. 4 • Awarding On : 01st Nov 2006 • Completed On : 25th Jul 2008 • Physical Progress : 100% • Financial Progress : 87% TCE: 457 Million • Dinning & Study Hall • Kitchen for Dinning & Study Hall • Awarding On : 15th May 2006 • Completed On : 30th Jun 2006 • Physical Progress : 100% • Financial Progress : 87% • Water Sump & Pump House • Awarding On : 01st Sep 2006 • Completed On : 16 Jun 2008 • Physical Progress : 100% • Financial Progress : 73% 25 August 2015

  6. Landscaping - Phase - 1 Area • Awarding On : 01stJan 2007 • Completed On : 19th Jan 2008 • Physical Progress : 100% • Financial Progress : 70% • Name Board and Developments • at entrance • Awarding On : 01st Jul 2007 • Completed On : 19th Jan 2008 • Physical Progress : 100% • Financial Progress : 35% • Temporary Sports Court • Awarding On : 15th Jan 2007 • Completed On : 27th Feb 2006 • Physical Progress : 100% • Financial Progress : 70% 25 August 2015

  7. Fiber Network (IT back-born at Phase 1 buildings) • Awarding On : 01st Dec 2007 • Completed On : 31st Dec 2008 • Physical Progress : 100% • Financial Progress : 97% • Vice Chancellor's Bungalow • Awarding On : 08th Sep 2008 • Completed On : 09th Mar 2010 • Physical Progress : 100% • Financial Progress : 98% • Play Ground (For 200m track) • Awarding On : 01st Apr 2007 • Completed On : 13th Sep 2009 • Physical Progress : 100% • Financial Progress: 63% 25 August 2015

  8. Internal Road Network (A,B & D) • Awarding On : 01st Mar 2007 • Completed On : 30th Mar 2009 • Physical Progress : 100% • Financial Progress: 66% • Lecture Hall + Lab (Block E) • Awarding On : 05th Sep 2008 • Completed On : 15th Mar 2011 • Physical Progress : 100% • Financial Progress : 65% • Lecture Hall + Lab (Block F - I) • Awarding On : 01st Jan 2009 • Completed On : 08th Mar 2010 • Physical Progress : 100% • Financial Progress: 65% 25 August 2015

  9. Lecture Hall + Lab (Block F - II) • Awarding On : 27th Apr 2010 • Completed On : 26 Jul 2011 • Physical Progress: 100% • Financial Progress: 65% • Lecture Hall + Lab (Block D) • Awarding On : 27th Apr 2010 • Completed On : 26th Aug 2011 • Physical Progress: 100% • Financial Progress:65% • Storm Water Drainage System • Awarding On : 30th Dec 2009 • Physical Progress: 65% • Financial Progress: 17% Ongoing 25 August 2015

  10. Quarters for Deans/ Registrar/ Bursar & Course Directors • Awarding On : 01st Dec 2011 • Completed On : 15th Feb 2013 • Physical Progress : 100% • Financial Progress : 77% • Staff Quarters (Studio Apartments) • Awarding On : 25th Nov 2012 • Completed On : 05th Mar 2013 • Physical Progress : 100% • Financial Progress : 50% • Roads and Landscaping • at Phase II Area • Awarding On :17th Dec 2009 • Physical Progress : 50% • Financial Progress : 41% Ongoing 25 August 2015

  11. Sports Center & Gymnasium • Awarding On : 30th Dec 2014 • Physical Progress : 25% • Financial Progress : 25% Ongoing • Pavilion • Awarding On :06th Aug 2015 • Physical Progress : 5% • Financial Progress : 5% • (Mobilization Advance) Ongoing • Cafeteria and Toilets • Awarding On : 27th Aug 2012 • Completed On : 26th Aug 2013 • Physical Progress : 100% • Financial Progress: 100% 25 August 2015

  12. Maintenance section • Awarding On : 08th Jan 2014 • Completed On : 08th Oct 2014 • Physical Progress : 100% • Financial Progress: 66% • Senate Building • Awarding On : 20th Mar 2013 • Physical Progress : 95% • Financial Progress: 85% Ongoing • Balance work Roads & Landscaping • Awarding On : 22nd Mar 2014 • Physical Progress: 65% • Financial Progress: 44% Ongoing 25 August 2015

  13. Waste water drainage & • treatment works (Job 01 & Job 02) • Awarding On :14th Oct 2010 / 17th May 2013 • Physical Progress : 85% • Financial Progress: 36% Ongoing • University Guest House • Awarding On: 05th Sep 2011 • Completed On: 20th Oct 2012 • Physical Progress: 100% • Financial Progress: 64% • University Guest House • Awarding On: 05th Nov 2012 • Completed On: 17th Aug 2013 • Physical Progress: 100% • Financial Progress: 96% 25 August 2015

More Related