Update: 1-4-2005

Update: 1-4-2005. Stony Brook Crew. Clean Room Progress. Laminar Flow Hood: In Place, Operating, New Filters arrived. Ready. Evaporator System: Evap Box Machining nearly complete. Railroad(s): “ToDo” next week. Want “Fake GEMs” Are there 4 spare frames at WIS?

stender
Télécharger la présentation

Update: 1-4-2005

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update: 1-4-2005 Stony Brook Crew

  2. Clean Room Progress. • Laminar Flow Hood: • In Place, Operating, New Filters arrived. • Ready. • Evaporator System: • Evap Box Machining nearly complete. • Railroad(s): “ToDo” next week. • Want “Fake GEMs” • Are there 4 spare frames at WIS? • Could put simple (no holes) Cu-Ni-Au kapton in place. • Desired for Dry runs.

  3. Vessels Status • Vacuum Storage: • End Flanges Done. • Need simple (Uni-strut) frame to hold in position. • Need to Assemble. • Gain Test Box: • Pump Identified (steal from Evap System). • Retooling needed for Scintillation Tests. • R. Lefferts, A. Sickles, A. Milov. • Old Glove Box: • Are we preparing Prototype for Run6????? • Gloves non-standard (need to “cut” std gloves). • Leaks profusely through bolt threads.

  4. Main Glove Box • Bids have not yet arrived. • New Bid process specifies two bids: • Short one (MBraun will bid ~$53k) • Long one (MBraun will bid ~$63k). • Time an issue…