1 / 12

2015 Bond Rate Guidelines for the Calculation of Land Reclamation Bonds on Coal Mining Operations

2015 Bond Rate Guidelines for the Calculation of Land Reclamation Bonds on Coal Mining Operations. MRAB Meeting January 22, 2015. 2014 AML Reclamation Grading Costs. 10 AML Reclamation Projects with Grading 4,612,457 Total Cubic Yards Average of 3 Lowest Bids was $.92 per Cubic Yard.

stevegray
Télécharger la présentation

2015 Bond Rate Guidelines for the Calculation of Land Reclamation Bonds on Coal Mining Operations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2015 Bond Rate Guidelines for the Calculation of Land Reclamation Bonds on Coal Mining Operations MRAB Meeting January 22, 2015

  2. 2014 AML Reclamation Grading Costs • 10 AML Reclamation Projects with Grading • 4,612,457 Total Cubic Yards • Average of 3 Lowest Bids was $.92 per Cubic Yard

  3. 2012 - 2014 AML Reclamation Grading Costs • Grading Costs Range from $.40 - $6.00 per Cubic Yard • Even distribution of grading frequency between $.80 and $1.00. Highest frequency at $1.00

  4. 2015 Bond Rate Summary (projected cost amount) • Grading (<500 Ft push) $.95 per Cu Yd • Grading (>500 Ft push/haul) $1.20 per Cu Yd • Selective Grading $1,700 per Acre • Revegetation $1,900 per Acre

  5. 2015 Bond Rate Summary (projected cost amount) • Tree Planting $2.00 per Tree. • Based on reclamation contract amounts rather than DCNR nursery stock price.

  6. 2015 Bond Rate Summary (projected cost amount) • Ditch Excavation $7.00 per Cubic Yd • Jute Matting $4.00 per Square Yd • HV Erosion Control $3.80 per Square Yd

  7. 2015 Bond Rate Summary (projected cost amount) • AASTO No. 1 $29.00 per Ton • AASHTO No. 57 $30.00 per Ton • R3 Rock Lining $33.00 per Ton • R4 Rock Lining $25.00 per Ton

  8. 2015 Bond Rate Summary (projected cost amount) • R5 Rock Lining $27.00 per Ton • Geotextile/Filter Fabric $2.80 per Square Yd • PVC Lining $12.00 per Square Yd

  9. 2015 Bond Rate Summary (projected cost amount) • Subsurface Drain $19.00 per Lineal Ft • Stage 3 Maintenance Bond Non-Cropland $100 per Acre • Stage 3 Maintenance Bond Pastureland or Hay $550 per Acre

  10. 2015 Bond Rate Summary (projected cost amount) • Stage 3 Maintenance Bond Cropland Row Crops $850 per Acre

  11. 2015 Bond Rate Effective Date • Effective Date is April 1, 2015 • Publish in PA Bulletin During February or March 2015

  12. Bruce CarlBureau of Mining Programs717-783-3516brcarl@pa.gov

More Related