EBT System Testing

Dean Fortin – Massachusetts WIC 23 July 2014. EBT System Testing. System Testing Objectives. Verify hardware Verify software Verify hardware/software interaction Verify system to system interaction Verified against defined requirements. System Requirements. Functional

Télécharger la présentation

EBT System Testing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Dean Fortin – Massachusetts WIC 23 July 2014 EBT System Testing

  2. System Testing Objectives • Verify hardware • Verify software • Verify hardware/software interaction • Verify system to system interaction • Verified against defined requirements

  3. System Requirements • Functional • Issue benefits to participants • Redeem benefits at vendors • Pay vendors for purchases • Non-functional • Accomplish task within specified time • Operate with specified number of users • Documentation

  4. WIC EBT Requirements • Universal MIS-EBT Interface Specification • WIC EBT Operating Rules • WIC EBT Technical Implementation Guide • Federal Register – Implementation Rules • NUPC Requirements

  5. System Design/Development • Project Kickoff Meeting • Team concept with one goal • Schedule milestones • Open Communications • Accountability • Joint Application Design Sessions • Requirements breakdown • Interface specification adjustment • Refine schedule

  6. Testing Process • Use Cases and Test Cases • Unit Testing • Integration Testing within each system • Functional Testing within each system • Testing Integration of Unfinished Systems • Schedule, communication, accountability • Special testing tools and utilities • Interface Test Scripts

  7. Using Test Results • Get results from each level of testing • Incorporate feedback into the development process • Weekly meetings • Each contractor (including WIC office) • Project Managers • Developers, Operations, Vendors, etc. • Daily touch point • Formal test results documented

  8. Communicating with FNS • Monthly EBT status call • Plans • Results • Status • Weekly call as Pilot approaches • Plans • Results • Status • Approval