1 / 10

Modesto Junior College Science Community Center

Modesto Junior College Science Community Center. Design Challenges. Floor Vibration Criteria Telescope Vibration Criteria Horizontal Drift Joint Spiral Stairs Steel Subcontractor – Walked Away Moment Frame – Grade Beam Interface Planetarium Door Widening. Floor Vibration Criteria.

tacey
Télécharger la présentation

Modesto Junior College Science Community Center

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Modesto Junior CollegeScience Community Center

  2. Design Challenges • Floor Vibration Criteria • Telescope Vibration Criteria • Horizontal Drift Joint • Spiral Stairs • Steel Subcontractor – Walked Away • Moment Frame – Grade Beam Interface • Planetarium Door Widening

  3. Floor Vibration Criteria • Lab Consultant: • W3 x 18 with 4 ½” normal weight concrete over the top of flutes; total thickness = 7 ½”. • Vibration Criteria was Excessive – Added an additional $1,000,000 in steel floor beam cost to the project – $500,000 per floor. • Compromise Solution – District not having vibration issues in current facility: • Floor Beams: • Design for 125 psf Live Load, Non-reducible • Limit deflection to: • L/240 DL + LL • L/360 LL Only • Design floor beams as “non-composite” then install Nelson studs @ 12” oc. Foundation Model: Design for 80 psf Live Load (reducible) & 20 psf partition load (Designs like this give engineers a bad name!)

  4. Telescope Vibration Criteria

  5. Telescope Independent Space Frame

  6. Horizontal Drift Joint

  7. Spiral Stairs

  8. Steel Subcontractor Disappeared! Total number of subcontractors on the project =63 Number of subcontractors that filed for bankruptcy during construction of the Science Community Center = 33 Impact of steel subcontractor going away: $2.4 million 4 ½ month project delay Steel pieces scattered across the project site.

  9. Moment Frame Column Base

  10. Planetarium “Door Widening”

More Related