1 / 9

AAPTP UPDATE

AAPTP UPDATE. March 2007. www.AAPTP.US. AAPTP Background. Program began 2004 Cooperative Agreement Auburn University Contractor Projects are awarded as subcontract to Auburn University Organizational structure similar to NCHRP Funding obtained for FY-04 thru FY-06. AAPTP Status.

tad-simpson
Télécharger la présentation

AAPTP UPDATE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AAPTP UPDATE March 2007 www.AAPTP.US

  2. AAPTP Background • Program began 2004 • Cooperative Agreement • Auburn University Contractor • Projects are awarded as subcontract to Auburn University • Organizational structure similar to NCHRP • Funding obtained for FY-04 thru FY-06

  3. AAPTP Status • 12 Projects Awarded • 1 Project in evaluation process • Funding available for 7 new projects (FY-06) • Approval and prioritization for 9 projects from FY-07 funds (not yet approved by Congress or FAA)

  4. Project Status Update FY-04 Projects Include: Rubblization, PG Binder, Superpave, SMA Longitudinal Joints, & Porous Friction Course Project to be complete in 2007: Rubblization, PG Binder, Longitudinal Joints and Porous Friction Course

  5. Project Status Update • FY-05 Projects • 05-01 Awarded to NCAT – Ray Brown • 05-02 Awarded to AMEC – Doug Hanson • 05-03 Awarded to AAT – Don Christensen • 05-04 Awarded to ARA – Harold Von Quintus • 05-05 Awarded to NICET – Ahmed Farouki • 05-06 Univ. of Nevada Reno – Peter Sebaaly • 05-07 Proposal being evaluated

  6. Project Status Update • FY-06 – Technical Panels being formed • 06-01 – Extension of 05-06 (Funds $330K) • 06-02 RFP March 2007 (Funds $150K) • 06-03 RFP March 2007 (Funds $190K) • 06-04 RFP April 2007 (Funds $190K) • 06-05 RFP May 2007 (Funds $190K) • 06-06 RFP June 2007 (Funds $100K) • 06-07 RFP August 2007 (Funds $195K)

  7. Proposed Project for FY-07 • 07-01 Improved Shear Strength to Accommodate Higher Tire Pressures • 07-02 Improved Mix Design Construction and Maintenance of Grooved HMA Airfield Pavements • 07-03 Guidelines for Design and Application of Tack and Prime Coat for Airport HMA Pavements • 07-04 Evaluation of Failure Mechanisms for HMA Airfield Pavements • 07-05 Mechanistic Properties of FAA HMA Standard Specification Materials

  8. FY-07 Projects (cont.) • 07-06 Use of Accelerated Laboratory Tests to Develop Improved Rutting Predictions Models for Airfield Pavement • 07-07 Model Data Base Collection of HMA Airfield Construction Data • 07-08 Development a Web Based Information System for Airfield HMA Best Construction Practices Manual • 07-09 Investigate Severity, Extent and Corrective Measures for Segregation on HMA Airfield Pavements

  9. Thank You! Questions?

More Related