Project Estimates Volatility of Material Costs

Project Estimates Volatility of Material Costs. California Transportation Commission Tab 7, Reference # 4.5 Action Item Presentation by: California Department of Transportation November 3, 2005. Recent Trends. Increasing Bids Increasing Costs and Volatility in the Materials Market

talor
Télécharger la présentation

Project Estimates Volatility of Material Costs

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Estimates Volatility of Material Costs California Transportation Commission Tab 7, Reference # 4.5 Action Item Presentation by: California Department of Transportation November 3, 2005

  2. Recent Trends • Increasing Bids • Increasing Costs and Volatility in the Materials Market • Decreasing Number of Bidders • Less Competition • Higher Prices

  3. Volatility of Material Cost

  4. Sample ProjectAsphalt Concrete PavementPercentage of Total Project Cost

  5. Bidding Summary from July 1 thru October 20

  6. Objectives • Improve Department’s Estimating Practices to Better Forecast Costs at time of Bid Opening • Get Better at Estimating Future Projects. • Vote the Correct Funds. • Outcome: Engineer’s Estimate at time of Vote Within 10% of Low Bid. • Improve Contractor Confidence that Reasonable Low Bids will be Awarded. • Ensure Contract Award (where reasonable). • Outcome: More Bidders, Greater Competition, and Lower Prices.

  7. Proposed Material Cost Adjustment Material Cost Adjustment Engineer’s Estimate

  8. Adjusted Call Number vs Actual Bids on Projects >$5M

  9. Update Engineer’s Estimate At Vote Monitor Monthly

  10. Materials Cost Update Enhanced Process • Office Engineer will Establish an Adjustment Forecast Reflecting Expected Material Cost at Bid Opening. • Apply Adjustment, if Needed, at Vote for Material Cost Forecast. • Monitor Estimate Monthly During Advertisement Period.

  11. Action to Restore Contractor Confidence Maximizing the use of delegated approval of supplemental funds requests (July action). • Outcome: Timely Award of Contracts. • Outcome: Faster Contract Awards • Outcome: Reasonable Low Bid will be Awarded.