Final Commissioning Activities for ECAL and HCAL in Cavern - June 2009
This document outlines the last commissioning activities for the ECAL and HCAL components in the cavern, conducted by Pascal Perret at LPC Clermont. Key activities included the re-installation of integrator boards, electronic maintenance, patch panel exchange, LED tuning, survey and alignment, and detector closing. The A-side activities occurred from June 19-22 and June 26-29, while C-side activities took place on July 1-2 and June 29-30, respectively. The planning for DCS readiness is also highlighted.
Final Commissioning Activities for ECAL and HCAL in Cavern - June 2009
E N D
Presentation Transcript
CALOCommissioningActivities 22 June 2009 Pascal Perret LPC Clermont
Activities in the cavern: Last Access! • ECAL: • Integrator boards re-installation and last checks: • ~1 day/side: • A-side: June 19-22 done • C-side: July 1-2 ? • HCAL: • Last checks: • ~1 day/side: • A-side: June 26-29 2pm • C-side: June 29-30 Pascal Perret - LPC Clermont
Activities in the cavern: Last Access! • PS: • LV patch panel exchanged: June 29 (A-side)-30(C-side) • VFE electronics maintenance: • A-side: June 29-30 • C-side: July 1 • PS/SPD: • LED tuning C-side? No news from Evgueni … • Survey & alignment: July 2-3 • Detector closing & survey: July 6-10 (according to M1) • Turbines exchanged … • By groups of 3 (3 spares!): 3/day ? • … Pascal Perret - LPC Clermont
Planning • DCS shouldbeready (in action!) as soon as possible … Pascal Perret - LPC Clermont