An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Strategic Sourcing Rosemont,IL 16 – 17 Feb 2010

  2. EGS Direct Material Purchases $137M FY10 NA $83M Europe $10M China $22M India $20M

  3. Key Performance Indicators $12M Mexico $3M EE

  4. FY10 – Sourcing Challenges • Keep Net Inflation in check • Support both strategic and tactical needs • Localize Supply Base • Simplify Supply Base • Lead Times, Lead Times, Lead Times • Indirect Projects

  5. Key Metals – Inflation Impact

  6. Latest Commodity Numbers Galvanized Steel Forecast FPC $ / Ton

  7. Major Savings Projects

  8. Organization

  9. Organizational Strategies • Monthly Meeting • Review PPV/OTP/Inventory/Quality, Supplier Reductions and Supplier Distress • Review eSourcing Projects • Top 25 Suppliers Performance Reports • Shared Drive • Major Project Timelines & Qualification Plans • Supply Base Reviews Upcoming • Key – consolidate “small spend” suppliers

  10. Supplier Consolidation Plan • 269 Suppliers identified for elimination from FY09 Spend • Key Projects Include • BH Consolidation – 48 • CO/MTY Consolidation – Est. 60 of 423 (205 < $10K in spend) • Distribution – 16 • Springs – 13 • Rubber – 22 (up to 47) • Stampings – 12 (up to 97) • Europe – 26 (up to 34) • Currently at 791 Suppliers through 4 Months • Still 564 “single location suppliers” more opportunities

  11. Current Supply Base supporting 2010 Mexico Operations Atizapan Suppliers Columbus / Birch Hill Suppliers Plants with Job Moves

  12. EGS Mexico – Spend Transition Plan

  13. EGS Mexico – Spend Transition Plan Reducing the Complexity while Localize !

  14. Lead Time Strategies • Localize – North America • Dual Source • Handle Spikes with Local Suppliers • Work with suppliers capable of US held Inventory • Set up Kanban when appropriate • Hold low cost / Long lead time items for K items at suppliers • Set up alternative suppliers and UL listings ahead of time

  15. Lead Time Projects

  16. Indirect Spend

  17. Supply Chain Summary • Team focused on • Savings / Supplier Reduction / Responsiveness • Team now regionalized to support both Strategic and Tactical needs • Team working closely with plant rationalization efforts