This document outlines the procedures for scheduled curtailments and their modifications. It specifies that notice of curtailments must be submitted at least one business day prior to the start date. Modifications to the curtailment schedule require at least 7 calendar days' notice, with 15 days for assets with a Minimum Interconnection Capacity (MIC) or Maximum Net Supply of 0.5 MW or more. Any changes to start and end dates must be communicated following these guidelines to ensure compliance and resource availability.
E N D
Scheduled CurtailmentsCancellations • Should be received at least one business day prior to start date of curtailment • Resource Availability should not reflect the curtailment • Day Ahead offers can be entered
Scheduled CurtailmentsModifications • Modification 1: • Delayed start date, same end date • Notice must be received at least 7 calendar days prior to changed start date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW) Start Date End Date Original Curtailment Modification 1: Later Start Date StartDate
Scheduled CurtailmentsModifications • Modification 2: • Same start date, earlier end date • Notice must be received at least 7 calendar days prior to changed end date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW) • Same requirements if curtailment extended past original end date (notice 7 / 15 calendar days prior to original end date) Start Date End Date Original Curtailment Modification 2: Earlier End Date EndDate
Scheduled CurtailmentsCurtailment Schedule Change • Change in Schedule: • Change to both start and end dates • Original curtailment will be cancelled, new curtailment entered • Notice must be received at least 7 calendar days prior to curtailment start date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW) Start Date End Date Original Curtailment Change: Different Start and End Dates Start Date EndDate