Grant contract and annexes

Grant contract and annexes. Training for Auditors Estonia/Latvia/Russia ENPI CBC Programme Riga, Tartu, 24-25 April 2012. Special conditions: main provisions. Take precedence over the annexes

tyson
Télécharger la présentation

Grant contract and annexes

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Grant contract and annexes Training for Auditors Estonia/Latvia/Russia ENPI CBC Programme Riga, Tartu, 24-25 April 2012

  2. Special conditions: main provisions • Take precedence over the annexes • Any addition/derogations to the General conditions applicable to EC financed grant contracts are specified inArt 7 of the Special Conditions Outline: • Article 1 – Purpose • Article 2 - Implementation period of the Action • Article 3 - Financing the Action • Article 4 - Narrative and financial reporting and payment arrangements • Article 5 - Contact addresses • Article 6 – Annexes • [Article 7 - Other specific conditions applying to the Action]

  3. Special conditions: annexes • Annex I: Description of the Action • Annex II: General Conditions applicable to European Community-financed grant contracts for external Actions • Annex III: Budget for the Action • Annex IV: Contract-award procedure • Annex V: Standard request for payment and financial identification form • Annex VI: Model narrative and financial report • Annex VII: Model report of factual findings and terms of reference for an expenditure verification of an EC financed grant contract for external actions • Annex VIII: Model financial guarantee • Annex IX: Standard template for Transfer of Assets Ownership

  4. Implementation and execution period

  5. Start of implementation • Distinguish between: • When the contract takes effect = date of last signature • When the Action starts= as specified in art. 2.2 of the special conditions: • The day following that on which the last of the two Parties signs OR • A later date

  6. Implementation period • Distinguish between: • When the implementation period ends: XX months after Action start date (art. 2.3 Special conditions) • When the execution period of the contract ends: • When final payment is paid by JMA OR • In any case at the latest 18 months after the end of implementation period

  7. Срок реализации и действия контракта

  8. Start of implementation • Costs are eligible only during implementation period • Except costs relating to final reports, expenditure verification and evaluation of the Action • Art. 7.2.11: incurrednotlaterthansubmission of the Finalrepot • Art. 7.2.11: In exceptionalcasesbefore the Action’sstart, butduring the executionperiod • Procedures to award sub-contracts for goods, services or works may be initiated before, but sub-contracts may NOT be concluded by the Beneficiary or its partners before Action start date! • Art. 7.2.11: In exceptionalcasesbefore the signature of the Grant contract, listed in the Art. 7.2.11

  9. Financing of the Action Eligibility of costs

  10. Eligible costs • Art.3.5, SC • In-kind costs are eligible only if it is: • an unpaid voluntary work • usage of the Beneficiary’s and/or the project partner’s own premises for implementation of the project activities • Pursuant to Art.14.5 contributions in kind are eligible and may be treated as co - financingby the Beneficiary and/or partners providing that these costs are justified in theDescription of the Action and included in the Action budget based on real costs,calculated on pro rata basis according to duly justified and clear method and backed upby evidence documents • In-kind contribution cannot exceed - 10% of the Beneficiary’s/ partner’s eligible expenditure and it cannot exceed the Beneficiary’s/ partner’s own contribution

  11. Financing of the Action Budget includes all eligible project costs, not just the ENPI CBC programme contribution Double ceiling for JMA financing (art. 3.2 Special Conditions), examples:

  12. Reporting and Payments

  13. Payments and Requests for payment • Art. 7.2.13 • Option 1: < 18 months AND < 300.000€ • Initial: 40% of the programme’s contribution • Further: not more than 40% of the programme’s contribution • Balance • Option 2: > 18 months OR > 300.000€ • Initial: 40% of the programme’s contribution for the first 12 months • Further: covering the needs for each 12 month period • Balance • Further pre-financing is conditioned by the proof of spending by the Beneficiary and its partners of at least 70% of the previous payment (and 100% of any previous payments) • Total pre-financingmaynotexceed80% of the programme’scontribution

  14. ReportingontheAction Art. 7.2.5 of SC Payment Option 1 Interim report Accompany every request for payment Final report No laterthan 3 monthsafterimplementationperiod Payment Option 2 Interim report No later than 1 month after each 6 months period Final report No laterthan 3 monthsafterimplementationperiod 14

  15. Expenditure verification • Art. 7.2.14 SC • Shall be attached to: • Any request for further pre-financing if Payment Option 2 • Any request for payment fo the balance • The expenditure verification report for the Balance covers all the expenses not covered by any previous EVR • Art. 7.2.3 SC • If EVR is not required – a list of financial and supporting documents and a printout of the project account showing project’s income and axpenditure and payments received

  16. Expenditure verification • Option 1: < 18 months AND < 300.000€ • Initial: 40% of the programme’s contribution • Further: not more than 40% of the programme’s contribution • List of supporting documents and printout of the account • Balance • Expenditure verification report • Option 2: > 18 months OR > 300.000€ • Initial: 40% of the programme’s contribution for the first 12 months • Further: covering the needs for each 12 month period • Expenditure verification report • Balance • Expenditure verification report

  17. Other important adjustments • Art. 7.2.1, the Art. 1.3. of General Conditions is adjusted • In duly justified cases, the contracting limit does not apply to Actions focused on infrastructure and investment activities. • Complementary provisions on the recovery • Specific provisions on procurement procedures • Art. 7.2.7, the Art. 6 of GC is supplemented with 6.5: • The Beneficiary shall send to the CA and the JTS information on the upcoming major or public Action events and procurement prior to event or procurement • Art. 7.2.15, the Art. 15.9 of GC is amended: • Any interest or equivalent benefit from pre-financing to be declared, assigned to the Action and deducted from the balance, except if MS (no 250.000€ ceiling)

  18. Questions? IN