An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FR-UK-IE Regional InitiativeCross-Border Balancing Procurement State of progress SG 7 - 03 December 2008 John Prime - Claude Perret

  2. Summary • Main issues stated at last meeting • Interim solution : state of progress • Enduring solution : state of progress

  3. Main issues stated at last meeting • BALIT Project (Acronym for “Balancing Inter TSO”) • Launched after the regulators’ approval of the NGET-RTE proposal • Interim solution, based on current BASA • Enduring solution, implementing complete process • Interim solution • BASA contract evolution in progress • The Interim solution will start after new French BM Rules approval by CRE • No practical solution to authorize NGET to formulate bids on the French BM • Target : New Rules should be approved Jan 2009 • NB : these new Rules will be convenient also for Enduring solution

  4. Main issues stated at last meeting • Enduring solution • NGET and RTE have started preliminary studies • Enhanced planning should be available in Nov 2009 • Remuneration of interconnector operators for use of infrastructure needs to be considered

  5. Interim solution : state of progress • BASA contract evolution • NG and RTE agreed on required changes • Draft worked out by NG • Ratification by RTE in progress • New French BM Rules • The consultation of stakeholders is over • The target for an approval by CRE in Jan 2009 remains relevant • TSO preparations on target for 01-Feb-09 commencement

  6. Enduring solution : state of progress • Technical solution for information exchanges • BALIT platform • Collects TSO to TSO tenders • Aggregates a Merit Order List • Manages the tendering and allocation process • Display results to each participant • Implementation guide for the BALIT Platform • Based on ERRP V2.r0 • Worked out by RTE, approved by NG • Invitation to tender for software development • In progress

  7. Enduring solution : state of progress • IS modifications • Analysis Phase in progress • Price generation (for each 50 MW bloc) • Sending of offers to BALIT Platform • Integration of offers received from BALIT Platform • Acceptance communication managing • Settlement process • Analysis Phase in progress • Operational process • Being finalised

  8. Enduring solution : state of progress • Remaining to be done • Development and coding Phase • Contractual aspects • Revision of BASA • Creation of TSO-TSO contract • Remuneration of interconnector operators • A four parties meeting is scheduled in December • Implementation targeted for November 09