1 / 11

MONALISA installation at the ATF2

MONALISA installation at the ATF2. ATF2 weekly meeting. Topics. MONALISA installation Survey requests Electronics requirements Vacuum pump + lines Laser hut location Request summary. Installation: Proposed timescale.

waylon
Télécharger la présentation

MONALISA installation at the ATF2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MONALISA installationat the ATF2 ATF2 weekly meeting

  2. Topics • MONALISA installation • Survey requests • Electronics requirements • Vacuum pump + lines • Laser hut location • Request summary ATF2 Meeting Oxford: MONALISA

  3. Installation: Proposed timescale • We will install the support frame at the start of the ATF2 summer shutdown 2009 • Our current estimate: July and August • This will be followed by installation of services across the ATF2 tunnel • vacuum • electronic / electrical • Total time required around 6 weeks ATF2 Meeting Oxford: MONALISA

  4. Expected installation order • Laying out floor connections for frame (1wk) • Building up frame around QDzero (1 wk) • Setting up vacuum systems (2 wk) • Vacuum testing (1 wk) • Installing interferometer components (1 wk) • Installing thermometer system (2 days) • Setting up laser system / DAQ (10 days) ATF2 Meeting Oxford: MONALISA

  5. Survey requests • Matt will bring a cardboard version of the intended metalwork footprint on QD0 • This will be discussed with KEK survey team • Verify space for mounting survey markers • We would like to request an initial survey of our assembled vacuum system in summer 09 • This will improve our 3 D model for coordinate reconstructions ATF2 Meeting Oxford: MONALISA

  6. Electronics requirements • A standard size electronics rack • Width (support holes) 465 mm apart • Height: approx 2 m. • Power @ 110 V • Total instrumentation power load expected to be approximately 3 kW • Estimate at least 6 to 8 power outlets • Route for electronics readout cables • to be discussed during ATF2 meeting week ATF2 Meeting Oxford: MONALISA

  7. Vacuum pump requirements • Is there an old scroll pump available at KEK? • Similar to Edwards ESDP12 • 15 m3 per hour • Ultimate pressure 1.6 x 10-2 mbar • 0.4 kW motor • KF25 inlet ATF2 Meeting Oxford: MONALISA

  8. Vacuum system • Pump location outside ATF2 beam enclosure • Requires vacuum line from pump to QDzero • We need to define the best location • Near the stairs (close to the “eels bedroom”) • Need to define route for vacuum line • during week of ATF2 meeting • Need assistance to weld pipes of vacuum line ATF2 Meeting Oxford: MONALISA

  9. Laser hut location • We would like • to assess hut location using latest drawings when Matt visits KEK. • To have office furniture for DAQ room at KEK • Define route for cables and optical fibres from experiment to hut • (during week of ATF2 meeting) • Are there any safety regulations concerning protection of optical fibres along their route? ATF2 Meeting Oxford: MONALISA

  10. Laser huts Requested MONALISA area Proposed MONALISA room Shintake laser room DAQ room ATF2 Meeting Oxford: MONALISA

  11. Summary • Schedule: Installation in July and Aug • Requests: • Answers to technical questions • Laser hut • Service routing • Scroll pump and vacuum lines • Electronics rack • DAQ room furniture • Initial survey of installed system ATF2 Meeting Oxford: MONALISA

More Related