1 / 10

LAND DEVELOPMENT BRANCH Land Support Project Update

LAND DEVELOPMENT BRANCH Land Support Project Update. 28 October 2008. 1. LAND SUPPORT PROJECTS. Engineers: Joint Project (JP) 154 - Joint Counter IED Capability JP 2110 - ADF CBRN Defence Mobility: Land 121 - Field Vehicles and Trailers JP 2048 Phase 3 LHD Watercraft

whitfield
Télécharger la présentation

LAND DEVELOPMENT BRANCH Land Support Project Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LAND DEVELOPMENT BRANCHLand SupportProject Update 28 October 2008 1

  2. LAND SUPPORT PROJECTS • Engineers: • Joint Project (JP) 154 - Joint Counter IED Capability • JP 2110 - ADF CBRN Defence • Mobility: • Land 121 - Field Vehicles and Trailers • JP 2048 Phase 3 LHD Watercraft • Logistics Information Systems: • JP 2077 - Improved Logistic Information Systems • Explosive Ordnance: • JP 2085 Ph 2/3 Explosive Ordnance Reserve Stocks • Other potential opportunities 2

  3. JP 154 Phase 1 Joint Counter Improvised Explosive Device Capability • Aim. Seeks to refresh the technology of all ADF Force Protection Electronic Counter Measures (FP ECM) capabilities primarily on an annual basis until 2012 to allow our Counter Improvised Explosive Device (CIED) capability to remain contemporary against extant and emerging threats. • Schedule. 1st Pass 2008, Year of Decision (YOD) from 2009. • Issues: • Schedule. High priority project means schedule is tight. • Future. Later phases of the project will consider further CIED systems. • Contact: MAJ Mark McAuliffe (02) 6265 4819.

  4. JP 2110 Phase 1ADF CBRN Defence • Aim. Seeks to deliver high payoff elements of a Chemical Biological Radiological Nuclear (CBRN) capability to the ADF to immediately increase operational capability in a contaminated environment: • Phase 1A - MOTS/COTS in-service chemical and radiological point source detectors. • Phase 1B - Systems such as Individual Protective Ensembles, Personnel, Vehicle and Sensitive Equipment Decontamination, Warning and Reporting System and Biological Detection. • Schedule: • Phase 1A. YOD 2009. • Phase 1B. YOD 2011. • Issues: • Schedule. High priority project means schedule is tight. • Scope. Diversity of ADF users an ongoing challenge. • Contact: LTCOL Warren Jolly (02) 6265 7875.

  5. Land 121Field Vehicles and Trailers • Aim. Seeks to provide field vehicles, modules and trailers to meet the mobility requirements of the ADF: • Phase 3. To consist of around 2300 Medium/Heavy vehicles (~ 50% protected), around 1100 unprotected Light/Lightweight vehicles and at least 250 Bushmaster Protected Mobility Vehicle. • Phase 4. To consist of around 1300 ‘Protected Mobility Vehicle – Light’ for command, liaison, recon and utility roles. • Phase 5. To consist of around 2200 unprotected vehicles from Light to Heavy for tactical training. • Schedule: • Phase 3. Government 2nd Pass announcement Aug 07. • Phase 4. To be announced. • Phase 5. Pre-1st Pass (mid-09). • Contact: MAJ Alistair Dickie (02) 6265 7837.

  6. JP 2048 Phase 3LHD Watercraft • Aim. JP 2048 Phase 3 seeks to provide up to 12 ship-to-shore connectors for use in the two new CANBERRA Class (HMA Ships CANBERRA and ADELAIDE) amphibious assault ships (LHD). • Schedule. 1st Pass 2009, YOD 2010. • Issues: • Schedule. Schedule driver is LHD introduction into service. • Request For Proposal. Respondents notified Jun 08. • Contact: MAJ Alistair Dickie (02) 6265 7837.

  7. JP2077 – 2DImproved Logistic Information System • Aim. Phase 2D seeks to address (up to) the eight highest priority residual Military Logistic Information System capability shortfalls through a program of work that will upgrade, replace, rationalise, and/or introduce new capability. • Schedule. RFP occurred Dec 07-Aug 08 and is now complete. Options development underway leading to Interim Pass mid-09. Restricted RFT (subject to approval) planned for 2009/10. ISD 2012-2015. • Budget. DCP ~$350M. • Contact: Mr Jim Godfrey (02) 6265 1101.

  8. JP 2085 PHASES 2/3EXPLOSIVE ORDNANCE • Aim. JP 2085 Ph 2/3 seeks to remediate the ADF’s EO stocks in order to ensure that joint forces have appropriate operational viability over a range of concurrent contingencies in accordance with Government expectations of Defence. • Schedule. 1st Pass early FY09/10. • Issues: • Supply/Facilities. Consideration maybe given to establish alternative supply mechanisms for some stock procurements. Support requirements, including storage facilities, are in scope. • Budget. $A450m-600m. • Contact: Ms Robyn Shephard (02) 6265 3163.

  9. Other Land Support Potential Opportunities • JP 2060 Phase 3 • Deployable Force Infrastructure • Aviation Ground Refuelling • Operational Personnel Tracking • Enhanced Gap Crossing 9

  10. Questions 10

More Related