1 / 8

COMS Nodal Commercial Systems Project Update

COMS Nodal Commercial Systems Project Update. COPs Meeting October 2007 Justin Rasberry & Bill Barnes. Agenda. COMS Requirements Update. Activities around baseline 2 synchronization are continuing, all 23 requirements have been updated and submitted for TPTF approval

wilsonlisa
Télécharger la présentation

COMS Nodal Commercial Systems Project Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COMSNodal Commercial Systems Project Update COPs Meeting October 2007 Justin Rasberry & Bill Barnes

  2. Agenda Texas Nodal

  3. COMS Requirements Update • Activities around baseline 2 synchronization are continuing, all 23 requirements have been updated and submitted for TPTF approval • All associated documentation (use cases, CSDs, test cases, etc) will be updated as Baselines approved • COPs personnel should stay abreast with COMS requirement changes. Texas Nodal

  4. COMS CSD Update • All COMS Conceptual System Design (CSDs) will be rolled into the v3.0(thru baseline 2) and submitted to TPTF following approval of the requirements Texas Nodal

  5. Nodal Statements and Invoices – Presentation Format • Finalize Settlement Statement presentation format • Approval at TPTF • Finalize Invoice presentation format • Payment due date and time • Terms in XML • Review Invoice presentation format • Oct COPs - CRR Auction Invoice, CARD Invoice, CRR BA Invoice • Nov COPs - Late Fee Invoices, Uplift Invoice Texas Nodal

  6. Development Update • Detailed Design on task • Final Draft 1 complete • Will continue to update with “As-Built” information throughout development cycle • Lodestar version 4.7 continues to stabilize • Corrected majority of major issues which impacted design and build strategies • Monitoring remaining issues and enhancements to ensure we stay on schedule • Additional engagement from Lodestar Executive Management has been achieved • Tactical response team in place to correct issues • Remains a risk to overall S&B coding delivery schedule • Risk probability reduced as major issues corrected • Lodestar metadata changes remain ongoing • Unit testing in progress • Initial testing at the Modular level and will “build up” to batch Texas Nodal

  7. Development Update • Most build packages consists of multiple modules • Modules aligned into business functional components (i.e. DAM Energy, DAM AS, CRR, etc.) • Target FAT completion by late 4th quarter 2007 • Target SAT completion by late 1st quarter 2008 • Currently, Lodestar S&B slated for EDS 3 & 4 • Statements and Invoice format for EDS 3 • Shadow Settlements EDS 4 (requires Extracts) • Settlements Go Live with 1st CRR auction Texas Nodal

  8. Questions ?? Justin Rasberry Manager, MO DPO Market Operations Divisional Projects Organization ERCOT (512) 248-3991 jrasberry@ercot.com Bill Barnes Manager, Settlements and Billing ERCOT (512) 248-6850 bbarnes@ercot.com Texas Nodal

More Related