An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PR50121_07 Retail Business Processes (RBP)Project Update A Sub-project of the Service Oriented Architecture (SOA) Initiative Retail Market Subcommittee Meeting

  2. Background • Objectives • Goal is to replace current SeeBeyond Retail Components with TIBCO EAI components to deliver a technology and framework improved scalability, reliability, stability & maintainability. RBP is one of 8 SOA Subprojects to replace SeeBeyond. • Drivers • Minimize or reduce operating failures produced from current SeeBeyond Application and Architecture. • Reduce maintenance costs associated with up-keep of SeeBeyond Application and Architecture. • Dependencies • PR50025 – Enhance ESIID Look Up on TML GUI has cross-impact with Retail TML Functions • PR50121_08 EndPoint Services has dependency with RBP as built on same framework and need schedule to stay in synch. • PR50059 Siebel Transition to ODS has dependency on RBP DDLs • PR50060 EIF Transition to ODS has dependency on RBP DDLs PR50121_07 RBP PPL Source: ERCOT Priority: 1.0 Rank: .08 Budget: $1-3M Program Area: RO

  3. Project Status • Project Status – Currently on target for Schedule, Scope, and budget • Project Phases • Initiation – Completed 08/01/2005 • Planning – Complete 05/08/2006 • Execution • Go-Live – 12/10/2006 weekend • Stabilization effort – 02/09/2007 • Closing – Target to complete February 2007 • Recent Activities As of 11/29/2006 • Core UAT Completed • Submit Final Market Notice • Completed Initial Technical Walk-thru • Next Steps • Continue Delta Siebel Data Conversion every weekend until Complete • Continue Delta EIF Data Conversion every weekend until complete • Continue Performance Load Testing • Final Technical Walk-thru 12/1/2006 PR50121_07 RBP PPL Source: ERCOT Priority: 1.0 Rank: .08 Budget: $1-3M Program Area: RO

  4. Milestones • Requirements (pens down) – Completed April 12, 2006 • Design (internal document) – Completed July 14, 2006 • Build – Completed July 28, 2006 for Core Components • Internal Testing – Target Completion Date of December 1, 2006 • Internal Training – Target completion of December 12/1/2006 (updated) • Production (Go live) – Weekend December 10, 2006 **Code Migration, Data Conversion, and Production Verification PR50121_07 RBP PPL Source: ERCOT Priority: 1.0 Rank: .08 Budget: $1-3M Program Area: RO

  5. Testing Status • Testing Schedule • Transaction Processing: Starts 08/28 - 100% complete (approx. 600 scripts) • Retail TML: Starts 10/02 - 100% (approx. 50 scripts) • Reprocessing: Starts 10/02 - 75% (approx. 70 scripts) • ETS Testing: Starts 10/02 - 83% (approx. 60 scripts) • Load/Performance Testing: (Rescheduled) Starts 11/22 - 90% • Monitoring Testing: Starts 11/13 – 90% • Defect Status (182 total to date as of 11/29/2006) • Code – 89 Only 74 of those have been TIBCO • Configuration – 25 • Environment – 42 • Invalid – 24 • Unknown (Under Review) – 2 PR50121_07 RBP PPL Source: ERCOT Priority: 1.0 Rank: .08 Budget: $1-3M Program Area: RO

  6. Implementation Weekend • RMS approval for SLA exception Migration Weekend DATE AFFECTED:  7:00 AM Friday, December 8, 2006 to 11:30 PM Sunday, December 10, 2006 Additional Information: • All transactions received by ERCOT will be held at NAESB.  Market Participants are encouraged to limit transaction submission during this timeframe to normal transaction processing volumes.  (ie. no annual validation).   *** NAESB will be offline from 8:00 AM to 9:00 AM Saturday, December 9, 2006 for a server reboot.  Transactions WILL NOT be accepted by ERCOT while NAESB is offline.  Market Participants should not submit transactions during this time. *** •  867 Transactions will NOT be forwarded during the outage weekend. • 997 Functional Acknowledgements will NOT be sent during the outage weekend. • Cancel/Notification batch process may run after 6AM on Monday, 12/11/2006. (if rollback) PR50121_07 RBP PPL Source: ERCOT Priority: 1.0 Rank: .08 Budget: $1-3M Program Area: RO

  7. Implementation Continued • MarkeTrak will not be available during the outage weekend. • Retail Components of TML and API will NOT be available including: • Report Explorer / Search Reports (Includes statements and extracts) • Find ESI ID • Find Transaction • Submit Transactions • USA Functionalities • EXTRACTS • Siebel Service Order Extract will not run during the migration.  Full extract received on Tuesday, 12/12/2006 will contain all Siebel Service Order history, including data from Friday thru Monday. • Data Conversion Load Mitigation: • Reduce the outage to the Market by ERCOT Go-Live with 3-6 months of 2006 descending transactional data (previously stored in Seebeyond TCH Database) • Phase in remaining years on following weekends. ETC by late December 2006 / January 2007 • Retail TML and API Find Transaction will be limited to Data Conversion Load

  8. Implementation Status Communication Migration Checkpoint Emails: • Friday 12/8/2006 - Notification all transactions have cleared • Saturday 12/9/2006 at approximately 8:00 PM – Migration Status email • Sunday 12/10/2006 4:00 PM – Go/No Go Decision **Conference Bridge** • Conference DN:     3822 (outside ERCOT dial 512-248-3822) • Conference Password:  1307 • Sunday 12/10/2006 – Notice that migration Rolled Back or Completed

  9. Questions / Contact Adam D. Martinez Mgr, Market Operations Divisional Projects Organization ERCOT (512) 248-3883 amartinez@ercot.com Hope Parrish PM, Market Operations Divisional Projects Organization ERCOT (512) 248-6522 hparrish@ercot.com