BUILDING THE FINDHORN WIND PARK

BUILDING THE FINDHORN WIND PARK. Findhorn Wind Park. Total capacity of 750kW = 176 kW after capacity factor. The planning process. Wind resource assessment Financial model RAF Application for planning permission Visual impact study Noise study Bird study. Cost: £100k - No guarantee!.

Télécharger la présentation

BUILDING THE FINDHORN WIND PARK

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BUILDING THE FINDHORN WIND PARK

  2. Findhorn Wind Park Total capacity of 750kW = 176 kW after capacity factor

  3. The planning process • Wind resource assessment • Financial model • RAF • Application for planning permission • Visual impact study • Noise study • Bird study Cost: £100k - No guarantee!

  4. Visibility of the proposed turbines

  5. The effect of other wind farms and proposals

  6. EXCAVATION

  7. ROTOR

  8. NARCELLE

  9. The annual output is 1,537 megawatt hours per annum

  10. Planning permission Granted 18 Jan. 05 1,537 MWhr/annum 350 homes 475,000 litres of oil 660 tonnes carbon dioxide

  11. Financial Model • ROC’s & LEC’s are about 50% of income • Cost of generating power = 1.6 to 5.9 pence/kWh