1 / 30

Ulysses History How Ulysses was built

Ulysses History How Ulysses was built. Table of Content. 1977 Out-of-Ecliptic 1979 -1982 ISPM Qualification Spacecraft 1983 ISPM Flight Spacecraft 1985 Recertification #1 1986 Launch Campaign #1 1988-1989 Recertification #2 1990 Launch campaign #2. 1977 Out of Ecliptic.

yamka
Télécharger la présentation

Ulysses History How Ulysses was built

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ulysses HistoryHow Ulysses was built

  2. Table of Content • 1977 Out-of-Ecliptic • 1979 -1982 ISPM Qualification Spacecraft • 1983 ISPM Flight Spacecraft • 1985 Recertification #1 • 1986 Launch Campaign #1 • 1988-1989 Recertification #2 • 1990 Launch campaign #2

  3. 1977 Out of Ecliptic • First announcement of a mission to study the north and south pole of the Sun was made 1959 and finally 1977 again, called “Out-of-ecliptic” • Study performed by Dornier System in 1977 and 1978 • The name International Solar Polar Mission (ISPM) was chosen. • Dornier submitted and won the proposal for this challenging spacecraft design • Later on during the run of phase C/D, a contest was held to choose another name. •  Winner was Professor Bertotti with the name “ULYSSES” • Remark: the price was – two bottles of Champagne

  4. 1978 ISPM

  5. 1979 - 1982 ISPM Qualification • The qualification was reached via a very luxurious approach by • A Structural model spacecraft • An Engineering Model spacecraft • A Qualification Model spacecraft • The structural model was used for a static load test to proof the strength of the structure •  an accident happened at the preparation: during lifting of the trolley, the s/c glided back onto the frame and as result, an RTG strut was damaged.

  6. 1981 ISPM SM Integration • Structure Model arrived at Dornier Cleanroom

  7. 1981 ISPM QM Integration • Qualification Model integration at Dornier

  8. 1979 - 1982 ISPM Qualification • The Electro Magnetic Compatibility Test at ESTEC (June 1982)

  9. 1979 - 1982 ISPM Qualification • The qualification Thermal vacuum / thermal balance test at Intespace, Toulouse (July – August 1982)

  10. 1979 - 1982 ISPM Qualification • The Magnetic Test at IABG (Sept 1982)

  11. 1979 - 1982 ISPM Qualification • After a successful testing a small drink became standard (here after magnetic test)

  12. 1979 - 1982 ISPM Qualification • The qualification Vibration test at IABG, Munich (Sep 1982)

  13. 1979 - 1982 ISPM Qualification • The qualification Acoustic Noise test at IABG, Munich (Sep 1982)

  14. 1979 - 1982 ISPM Qualification • All qualification tests have been successfully passed and the go-ahead for the flight model was given. • Some technical data of Ulysses • Mass 367 kg • Dimensions 3,24 x 3,33 x 2,14 meters • Power 284 W at begin of mission, source RTG • Communication High Gain antenna 1,65m with 20 W X-band transmitter • Data Handling Data storage 45 Mbit tape recorder (2 off) • Reaction Control System with 33,3 kg of Hydrazine • AOCS Spin stabilized (5 rpm) with sun sensors and nutation dampers • Mechanism 1 radial boom 5,5m, 1 axial boom 7,5m •  Designed for a life time of 5 years

  15. 1979 - 1982 ISPM Qualification • Work at the Check-out Station

  16. 1983 ISPM Flight Spacecraft • The flight acceptance testing followed the same approach as for the qualification model • The following tests were performed: • Thermal vacuum / thermal balance test at Intespace, Toulouse (July – August 1983) • Electro Magnetic Compatibility Test at ESTEC (Sept1983) • Magnetic Test at IABG (October 1983) • All tests have been successfully passed but the launcher (Shuttle) was not ready and a new, unexpected phase started  Storage

  17. 1983 ISPM Flight Spacecraft • The flight model spacecraft has undergone a magnetic test at IABG successfully

  18. 1983 ISPM Flight Spacecraft Ulysses is put into storage after his flight acceptance tests (Dec 1983)

  19. 1985 Recertification #1 • In 1984, NASA announced a launch date for Ulysses in May 1986 • Therefore, a recertification phase started in January 1985 and lasted till December 1985 with a complete verification programme. This phase was performed in the ESTEC premises. • Some Instruments were returned 1983 for upgrading internally and had to be integrated and functionally tested again during this period. • In December 1985 everything was ready and Ulysses was shipped to the Kennedy Space Centre. The team arrived January 3, 1986.

  20. 1986 Launch Campaign #1 • The launch campaign commenced in January 1986 with the full team deployed to the Kennedy Space Centre, Florida - USA • All final functional testing was running well till January 28, when the accident with the Orbiter Challenger happened  continuation for Ulysses was open. • Work had continued for some weeks at KSC, but then finally stopped by NASA and Ulysses brought back to Europe  another storage period was initiated with an open status • Most of the instruments were returned to the Investigators for special calibration work

  21. 1988 - 1990 Recertification #2 • The recertification phase #2 started beginning 1988 until March 1990. • It contained a short thermal vacuum test at ESTEC and a spin balance test. • This test was necessary, because the launcher approach was changed from Centaur upper stage to IUS and PAM-S, which had a spin rate of 60 rpm before separation of the spacecraft.

  22. 1988 - 1990 Recertification #2 • Interface Clarification Meeting at McDonald Douglas (1988) with PAM-S

  23. 1988 - 1990 Recertification #2 • Visiting the Experimenters in USA 1988, before re-delivering to Europe

  24. 1988 - 1990 Recertification #2 • The end of the recertification phase at ESTEC in March 1990

  25. 1990 Launch Campaign #2 • The launch campaign started in May 1990 and finished with the successful launch on 6 October 1990 • The spacecraft was transported by a flight from Amsterdam to Orlando, Florida and then by trucks to the Kennedy Space Centre. • Unloading of the trucks was performed by the “heavy gang” of the KSC, but also the entire team has been involved.

  26. 1990 Launch Campaign #2 • Men at work

  27. 1990 Launch Campaign #2 Ulysses inside the Shuttle Cargo Bay on top of the IUS and PAM-S

  28. 1990 Launch Campaign #2 • The Shuttle Discovery (STS-41) ready for take-off

  29. 1990 Launch Campaign #2 • The ULYSSES Launch Team

  30. The Shuttle Patch 1990 Launch Campaign #2

More Related