US Army Corps of Engineers Budgeting Process. Sherry L. Adams Project Manager, Huntington District. STEP 1 - Initial Problem Identification. Lock / Dam Replacement - Inland Waterways System. Salmon Mitigation. Waterfront Development. Environmental Infrastructure Needs.

zahi
Télécharger la présentation

US Army Corps of Engineers Budgeting Process

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

  2. STEP 1 - Initial Problem Identification Lock / Dam Replacement - Inland Waterways System Salmon Mitigation Waterfront Development Environmental Infrastructure Needs Environ. Restoration Port / Harbor Deepenings Flooding Beach Erosion/Hurricane Protection Wetland Losses Ecosystem Restoration Water Supply Navigation Environmental Infrastructure Needs • “High Priority” Missions: • Flood Damage Reduction • Commercial Navigation • Ecosystem Restoration Letter to Corps District Office Inform Congressional Representative

  3. STEP 2 - Congressional Study Resolution / Authorization Passage ~ 2-yr. Intervals WRDA Bill • Authority - Congress! • Study Resolutions • WRDA Bills • Standing Authorities • Appropriations Bills ( Step 1 ) Member Have we studied the problem before? Environment & Public Works Committee Transportation & Infrastructure Committee OR Senate Resolution House Resolution - Signed by President

  4. STEP 3 - Initial Study Funding Coordination DIVISION WRDA HR/SR HQUSACE (Step 2 ) Budget Cycle 1/ President’s Budget ( G I ) • “High Priority” Missions • Flood Damage Reduction • Navigation • Ecosystem Restoration

  5. HQ Provides Budget Guidance ( Mar ) HQ Review & Approval ( May -Jun ) OMB Provides Budget Guidance ( Jan ) Field Offices Develop Program Requirements ( Apr - May ) Funding Alloc. To Field Offices ( Oct - Dec ) Budget Cycle Budget Presented to Sec. Army (Jul - Aug ) Budget Submitted to OMB ( Sep ) Cong. Hearings ( Mar - Apr ) OMB Passback ( Nov ) President Signs Approp. Bill ( Sep - Oct ) Appropriations Bills ( Jul - Sep ) President’s Budget to Congress ( Feb )

  6. Continuing Authority Program (CAP) • Projects with smaller scope, cost and complexity • Delegated authority to design and construct without specific Congressional authorization

  7. Existing CAP Funding Policies • Complete existing construction projects • No new project cooperation agreements • Congressional authorization for start or continuation of study (Naming or earmark)