Presentation to Jefferson Township Public Schools for Feasibility Study. Agenda. Background Findings Recommendation Options Timelines. Background. Over 3,600 Students 8 Facilities Jefferson Twp HS Jefferson Twp MS White Rock ES Stanlick ES Milton Pre-K Cozy Lake ES
E N D
Presentation • to • Jefferson Township Public Schools • for • Feasibility Study
Agenda • Background • Findings • Recommendation Options • Timelines
Background • Over 3,600 Students • 8 Facilities • Jefferson Twp HS • Jefferson Twp MS • White Rock ES • Stanlick ES • Milton Pre-K • Cozy Lake ES • Briggs ES • Drummond K • Serving Lake Hopatcong, Lake Shawnee, • Oak Ridge and Milton communities
Option 1: • Board Offices move to Drummond School • Central Storage moves to new location to be determined • Kindergarten remains at Drummond School • Pros: • Low Costs – Does not require Referendum • Short Timeframe • Least Disruptive – All students remain in current locations • Cons: • Does not accommodate Central Storage • Does not accommodate existing day care center • Does not address any educational needs • Does not accommodate full day Kindergarten
Option 2: • Board Offices move to Drummond School • Central Storage moves Drummond School • Kindergarten moves to Briggs School • Pros: • Board Offices and Central Storage are accommodated • Can accommodate existing day care center • Low Costs – Does not require Referendum • Short Timeframe • Administrative costs are reduced from two to one school • Cons: • Students are relocated • Does not address any educational needs • Does not accommodate full day Kindergarten
Option 3: • Board Offices move to Drummond School • Central Storage moves Drummond School • Kindergarten moves to Briggs School • Expand Briggs to accommodate full day Kindergarten • Expand Milton to accommodate full day Kindergarten • Expand Cozy Lake to accommodate multi-purpose functions • Pros: • Board Offices and Central Storage are accommodated • Administrative costs are reduced from two to one school • Addresses all educational needs • Accommodates full day Kindergarten • Cons: • Students are relocated • Higher costs - Requires Referendum • Requires longer timeframe
Timelines • Option 1: • Reconfigure Drummond School Summer 2010 • Relocate Board Offices to Drummond Summer 2011 • Vacate leased space Fall 2011 • Option 2: • Reconfigure Drummond School Summer 2010 • Relocate Kindergarten to Briggs School Summer 2011 • Relocate Board Offices to Drummond Summer 2011 • Vacate leased space Fall 2011
Timelines • Option 3: • Reconfigure Drummond School Summer 2010 • Start Referendum Planning Fall 2009 • Submit Schematic Plans to NJDOE Spring 2010 • Referendum December 2010 • Relocate Kindergarten to Briggs School Summer 2011 • Relocate Board Offices to Drummond Summer 2011 • Start Construction on Additions Summer 2011 • Vacate leased space Fall 2011 • Complete Construction on Additions Summer 2012