Beam for SeaQuest/E-906 Michael Geelhoed

Beam for SeaQuest/E-906 Michael Geelhoed. G2 to NM1 Bermpipe. Red: Berm Pipe. Green: Bermpipe Flange. Blue: G2 Enclosure. Yellow: G2 Vac pump St. Feb 1st. March 1st. April 1st. May 1st. June 1st. Vacuum Issue. Bermpipe Solution. NM1 Enclosure. G2 Enclosure.

zea
Télécharger la présentation

Beam for SeaQuest/E-906 Michael Geelhoed

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Beam for SeaQuest/E-906 Michael Geelhoed

  2. G2 to NM1 Bermpipe Red: Berm Pipe Green: Bermpipe Flange Blue: G2 Enclosure Yellow: G2 Vac pump St. Feb 1st March 1st April 1st May 1st June 1st Vacuum Issue Michael Geelhoed 2/20/12

  3. Bermpipe Solution NM1 Enclosure G2 Enclosure Sleeve the Bermpipe Michael Geelhoed 2/20/12

  4. G2 to NM1 Bermpipe Bermpipe monitoring port – N01 upstream Michael Geelhoed 2/20/12

  5. G2 to NM1 Bermpipe Bermpipe grout Michael Geelhoed 2/20/12

  6. G2 to NM1 Bermpipe G2 Enclosure NM1 Enclosure Grout in the Bermpipe

  7. G2 to NM1 Bermpipe Grout removal in Bermpipe Michael Geelhoed 2/20/12

  8. G2 to NM1 Bermpipe Grout Removal techniques Michael Geelhoed 2/20/12

  9. G2 to NM1 Bermpipe G2 Enclosure NM1 Enclosure Getting beam through the Bermpipe

  10. G2 to NM1 Bermpipe • Helium filled Berm pipe is the plan • Upon testing leak rate at positive pressure there was no leak. • Tried pumping down with pumps and bad “O” rings = 1.3 Torr • Pump down with good “O” rings < 1 Torr • Helium filled Berm pipe is now the back-up plan • Current plan is to run with < 1 Torr vac berm pipe Two options for the Bermpipe medium Michael Geelhoed 2/20/12

  11. Paperwork My understanding of the process* • Shielding Assessment in the hands of the SA Committee • Will take until Tuesday 2/21/12 to review SA • SAD has gone through the SAD Committee • Once both documents are approved & signed • AD Division Head approves & signs • ES&H Division Head approves & signs • DOE local office approves & signs Michael Geelhoed 2/20/12

  12. Finishing touches • ESS Interlock testing of entire NM beamline enclosures (complete) • Interlock testing of Radiation monitors (complete) • Operating/Safety/ Warning limits calculated • AD Division Department Heads approvals & signatures • AD RSO approval & signature • AD Division Head approval & signature Michael Geelhoed 2/20/12