Team HEaTT. Thermal Protection System Testing in High Enthalpy Facility. Progress Report #2. Richard French Vitaliy Grigoryev November 3, 2005. Summary. Schedule Update Facility update Test Materials. Schedule. Facility Overview.

zelia
Télécharger la présentation

Thermal Protection System Testing in High Enthalpy Facility

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Team HEaTT Thermal Protection System Testing in High Enthalpy Facility Progress Report #2 Richard French Vitaliy Grigoryev November 3, 2005

  2. Summary • Schedule Update • Facility update • Test Materials

  3. Schedule

  4. Facility Overview A – Diffuser; B – Test Section; C – Heat Source; D – Specimen Mounting; E – Test Specimen; F – Ventilation Fan; G – Data Acquisition System

  5. Facility Smoldering Tunnel Test Section Fan Diffuser

  6. Facility Update • Smoldering tunnel • - new fan driver motor ordered (right Chris?) • 500,000 BTU Torch and mounting - Complete - large fuel tank needed • Steel Test Stand - Complete • Instrumentation/Data acquisition - Doric Trendicator and Multipoint selector - thermocouples to be fabricated in-house

  7. Instrumentation

  8. Test Materials • Shuttle Tile Request Pending • - Expected delivery 2 weeks • Exotic Metals and Ablator - Niobium sample Friday • Ablator

  9. Test Materials

  10. Thanks QUESTIONS? TEAM HEaTT