An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Wastewater Treatment CVEN 451, Public Works Engineering Team Members: Kenneth Anton Roy Aviles & Elkin Mosquera

  2. Wastewater Treatment • Objective: To provide sewage treatment for a subdivision development of 10,000 people. • Assumptions • Four family members per house (2,500 units) • ¼ acre plot size (625 acres) • Wastewater generation is 100 GPD/CAP (1 MGPD) • Period of analysis is 30-years • Interest rate used is 7% • 67-year physical life of infrastructure

  3. Wastewater Treatment

  4. Wastewater Treatment • Option 1: New wastewater treatment plant (WWTP). • Capital investment includes land purchase, design, and construction cost

  5. Wastewater Treatment • Option 2: Expansion of Lick Creek WWTP. • Capital investment includes design and construction of expansion & O&M is a prorated cost

  6. Wastewater Treatment • Benefit of Option 1: A new wastewater treatment plant will support planed development in southern College Station. • Benefit of Option 2: Land zoned for another purpose will not need to be acquired and rezoned since existing plant will be used. • Recommendation: The recommended and lowest life-cycle cost (LCC) alternative is option 2, expansion of the Lick Creek Wastewater Treatment Plant. This option has an estimated Capital Investment cost of $16.3 M and LCC of $26.4 M.

  7. Action Items • Municipal bond rate – 7% 20-year rate • Option 1 Capital Investment - $22.8 M ($35.6 M NPV) • Option 2 Capital Investment - $16.3 M ($26.4 M NPV) • Sewage line cost *price of pipe from U.S. Plastic Corporation *price of installation costs from RS Means Manual ($11.00/ft/inch of pipe diameter)

  8. Action Items • Pipe sizes necessary for flow • Duration of new construction option is 2-years • From approval to end of construction