1 / 11

DØ RunIIb Trigger Upgrade Technical Progress

DØ RunIIb Trigger Upgrade Technical Progress. WBS 1.2 Darien Wood, Northeastern Univ. for the DØ Trigger Upgrade Group. WBS 1.2: Trigger Upgrade H. Evans (Columbia), D. Wood (Northeastern). WBS 1.2.1: Level 1 Calorimeter M.Abolins(MSU), H.Evans(Columbia), P.LeDu (Saclay).

zoltin
Télécharger la présentation

DØ RunIIb Trigger Upgrade Technical Progress

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DØ RunIIb Trigger UpgradeTechnical Progress WBS 1.2 Darien Wood, Northeastern Univ. for the DØ Trigger Upgrade Group

  2. WBS 1.2: Trigger Upgrade H. Evans (Columbia), D. Wood (Northeastern) WBS 1.2.1: Level 1 Calorimeter M.Abolins(MSU), H.Evans(Columbia), P.LeDu (Saclay) WBS 1.2.2: Level 1 Cal-track match K. Johns (Arizona) WBS 1.2.3: Level 1 Tracking M. Narain (Boston) WBS 1.2.4: Level 2 Beta upgrade R. Hirosky (Virginia) WBS 1.2.5: Level 2 STT upgrade U. Heintz (Boston) WBS 1.2.6: Trigger Simulation M. Hildreth (ND), E. Perez (Saclay) Outline Level 1 projects underway • Level 1 Calorimeter • Level 1 Cal-track matching • Level 1 Tracking • Trigger simulations Level 2 projects (not discussed here) • L2 Beta upgrade & STT upgrade • Later start in schedule • VTM’s procured for STT (part of larger order)

  3. Saclay ADC+Digitial Filter (ADF) ADF timing distribution board Analog splitter (for in-situ tests) ADF Crate/backplane Nevis Trigger algorithm board (TAB) Global Algorithm Board (GAB) Crates for TAB/GAB Test system for ADF-to-GAB cables WBS 1.2.1: Calorimeter Trigger Upgrade

  4. ADF: Saclay • ADF prototype schematics • All components chosen • Should be verified in a few weeks: end of prototype design • ADF prototype PCB design • Layout should start in about 1 week • Expect 3-4 weeks for layout

  5. Analog Splitter: Saclay & MSU • Analog splitter: allows in-situ test of digital filtering with real signals • Designed and tested at Saclay • Shipped to MSU Dec 20th: tested there • Installed in DØ L1Cal trigger (run IIa) during current shutdown • Noise tests in progress • Tests with beam (w/ splitter vs. w/o splitter) to follow

  6. TAB prototype: Nevis • Design essentially finished (mod’s driven by layout) • Layout/Schematics well advanced • Recent design issues • Use thresholds to deal with digital filter signal truncation • ADF-to-TAB cable mapping scheme adopted • Density of cables → no room for standard VME backplane • Slow communication w/ TABs & GAB designed • Full access to TAB/GAB using VME-transparent interface • Timing/control signal distribution

  7. Transatlantic communication & plans • Trigger Workshop held Nov 4-6 at Saclay • Participants: Engineers & physicists from Saclay, Columbia, MSU, Brown, NeU • Many decisions made about ADF-TAB data transfer, system commissioning • Integration plans • ADF + TAB prototype integration tests scheduled at Fermilab this summer • More detailed plan for commissioning of final system is being developed

  8. Cal-Trk match: Arizona • Uses “L1mu” electronics, apart from specialized “flavor board” • Flavor board (MTFB) prototype design >90% complete • Some procurements anticipated for next month MTFB (scint flavor)

  9. L1 CTT: Boston Univ. • Firmware design for target algorithm began in Nov • “front end” and “back end” code from Run IIa rewritten – latency reduced • Ongoing work on maps of single fibers

  10. Simulation • Studies of effects of trigger tower thresholds on L1cal global sums (missing ET) • L1Cal tau algorithm included in trig sim • Output of Run IIb L1 cal interfaced to standard DØ framework simulation package • Simulation of Cal-track matching progressing • CTT as-built geometry and beam offsets incorporated into simulation • Beam offsets up to ~1mm to not affect efficiency of Run IIb equations

  11. Summary • L1cal • ADF and TAB prototypes near the end of design phase – layouts soon • Analog splitter installed at DØ • Integration tests planned for Summer • L1 cal-track • Design of prototype flavor board nearly complete • L1 CTT • Progress in firmware – on schedule • Simulation • Continued support of design efforts and development of standard simulation packages

More Related