An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LEONARDO TRANSFER OF INNOVATION PROJECT “MEDIA TECH: The future of media industry using innovative technologies” No. LLP-LdV-ToI-11-CY-1671107 Further WP tasks 2nd meeting: 16 -17/7/2012 London Stella Ioannidou, Sigma TV

  2. WP 3(M6 – M10) March 2012 – July 2012Ea Media Solution LeaderDevelopment of course material and adjustment of innovation Tasks • Selection of the final training content by all partners(specify needs) • Realization of curricula for each training topic (translated in Greek, Spanish, Italian) (by 30/07/2012)

  3. Further Work Packages and relevant time Framework WP 4 (M11 – M18) August 2012 – March 2013 • Testing of innovation and organisation of actual training Leader IFI WP 5 (M19 – M22) April 2013 – July 2013 • Development of the final training package Leader SIGMA

  4. WP 4(M11 – M18) August 2012 – March 2013IFI LeaderTesting of innovation and the actual training Aims • Deliver the training programs to 30 people in each country • Fulfill the testing of the training content • Quality of the training program • Identify key successes and point out areas which require further improvement

  5. WP 4(M11 – M18) August 2012 – March 2013IFI LeaderTesting of innovation and the actual training Tasks • Testing training material (details of training programme) 30 people will participate in each country. 50 hours of training within a 4-month period(by 15/01/2013) • Ea Media Solutions will visit Cyprus, Greece, Italy and Spain to supervise the training and participate as trainer. each partner will employ its own trainers, which will be trained by Ea Media Solutions experts in media and media consultants will be employed by each country following the study of the material provided by Ea Media Solution (by 15/01/2013)

  6. WP 4(M11 – M18) August 2012 – March 2013IFI LeaderTesting of innovation and the actual training Tasks • Preparation of 1st evaluation questionnaire (by P1) (by 10th December 2012) • Presentation of the 1st evaluation questionnaire results (3rd meeting presented by January 2013) • Preparation of 2nd questionnaire for evaluation (by P1) (before the 3rd meeting in Italy)

  7. WP 4(M11 – M18) August 2012 – March 2013IFI LeaderTesting of innovation and the actual training Tasks • Participants will complete the 2nd questionnaire (2 months after the evaluation of 1st questionnaire) • Preparation of country evaluation report (by each partner) (by March 2013) • Quality evaluation of the training program by all partners-overall evaluation report (by P0, with the help of P3) (by 30/03/2013)

  8. WP 5(M19– M22) April 2013 – July 2013 SIGMA LeaderDevelopment of the final training package Aims • Development • Translation (Greek, Spanish, Italian) • Publication

  9. WP 5(M19– M22 April 2013 – July 2013SIGMA LeaderDevelopment of the final training package Tasks • Development of corrected package (by 01/05/2013) • Necessary changes of the training package (by 15/06/2013) • Final version of training package translated in each partner’s language (by 01/08/2013) • Presentation of results of testing and consolidated evaluation report (4th meeting, by 01/08/2013) • Designing and setting up the e-learning platform (by ATC) (by 01/08/2013)

  10. Current Work Packages WP 1 (M1 - M24) October 2011 – September 2013 • Project management Leader SIGMA WP 6(M1 – M24) October 2011 – September 2013 • Quality assurance and evaluation Leader ATC WP 7(M1 – M24) October 2011 –September 2013 • Dissemination and exploitation of project results Leader SIGMA

  11. WP1(M1 – M24) October 2011 – September 2013SIGMA LeaderProject management Aims Deliverables on time Monitoring progress Manage contingencies Inform partners on relevant developments Planning partners' meetings Achievement of the expected results Financial management Preparation and submission reports to the NA

  12. WP 6(M1– M24) October 2011 – September 2013ATC LeaderQuality assurance and evaluation Aims • Development and contribution to all work packages • Creation quality products • Fulfillment project objectives • Critical review • Creation and innovation approaches • Evaluate documentation throughout the project • Active partnership / meaningful dialogue

  13. WP 6(M1– M24) October 2011 – September 2013ATC LeaderQuality assurance and evaluation Tasks • Analysis and feedback about the the training material • Evaluate documentation throughout the project

  14. WP7(M1– M24) October 2011 –September 2013SIGMA LeaderDissemination and exploitation of result Aims • Promotion of the results of the project • Dissemination of action plan • Achievement in a balanced geographic spread of dissemination • Create, maintain, promote project’s website • Development of an exploitation/business plan

  15. WP7(M1– M24) October 2011 –September 2013SIGMA LeaderDissemination and exploitation of results Tasks • Newsletters (2nd by 20/12/2012 and 3rd by 30/06/2013) • Development of online training course (by 01/08/2013) • Design, printing and distribution of leaflets and poster (by 01/09/2013) • Articles published in magazines and newspapers (by 15/09/2013) • Organisation of final dissemination event in each partner country (by 15/09/2013)

  16. Partners’ Meetings III Meeting in January 2013ITALY IV Meeting in August 2013GREECE (final one)