1 / 35

i2 SCM Factory Planner

助教:鄭歆蓉 ( 分機: 7656) 研究室: MA004 ( 電子化企業實驗室 ) Email : D9701001@mail.ntust.edu.tw. i2 SCM Factory Planner. 電子化企業概論實習 Week 2 for i2 SCM. 課 程 大 綱. Week 1 複習 了解 i2 的 Finite Capacity Planning( 有限產能 ) 附註. Week 1 複習. 詳如 Week 1 實習講義。 - 安裝 i2 軟體 - 建置基本資料 (Input Data). Week2 課程目標.

Télécharger la présentation

i2 SCM Factory Planner

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 助教:鄭歆蓉 (分機:7656) 研究室:MA004 (電子化企業實驗室) Email:D9701001@mail.ntust.edu.tw i2 SCM Factory Planner 電子化企業概論實習 Week 2 for i2 SCM

  2. 課 程 大 綱 • Week 1 複習 • 了解i2的Finite Capacity Planning(有限產能) • 附註 E-Business Lab, IM, NTUST

  3. Week 1 複習 • 詳如Week 1實習講義。 - 安裝i2軟體 - 建置基本資料(Input Data) E-Business Lab, IM, NTUST

  4. Week2課程目標 • 了解i2的有限產能(Finite Capacity,CAO)的意義,並將無限產能規劃結果,轉換為有限產能的規劃。 E-Business Lab, IM, NTUST

  5. About CAO • Constraint Anchored Optimization (CAO) :CAO為一平衡程式,以自動化的方式,平衡超出產能負荷的Resource。 E-Business Lab, IM, NTUST

  6. Finite Capacity • Reasons for Capacity Balancing • Eliminate resource overloads • Maintains satisfactory due date performance if possible • Without violating material constraints E-Business Lab, IM, NTUST

  7. Step 1: 選擇要平衡的Resource (有超出負荷Resource) CAO 的步驟 超出產能 E-Business Lab, IM, NTUST

  8. (說明產能短缺的部分) 表示發生 產能短缺 M2出現 產能短缺 E-Business Lab, IM, NTUST

  9. LPST Plan Start Time CAO 的步驟 • Step 2:要選擇哪一個工作來優先平衡? CAO priority = LPST – Plan Start Time 所計算出來的CAO priority值越小則它的優先權越大。 E-Business Lab, IM, NTUST

  10. CAO 的步驟 Step 3: Pull-Offload-Push in this bucket. (先往前推) 1 2 3 4 5 6 7 E-Business Lab, IM, NTUST

  11. CAO 的步驟 Step 3: Pull-Offload-Push in this bucket. 1 2 3 4 5 6 7 E-Business Lab, IM, NTUST

  12. CAO 的步驟 Step 3: Pull-Offload-Push in this bucket. 1 2 3 4 5 6 7 E-Business Lab, IM, NTUST

  13. CAO 的步驟 Step 3: Pull-Offload-Push in this bucket. 再繼續做平衡,重複剛剛的動作 1 2 3 4 5 6 7 E-Business Lab, IM, NTUST

  14. CAO 的步驟 Step 4:選擇下一個時間區塊來平衡 Step 5:假如此Resource尚未平衡,則再回到 Step2 Step 6:檢視被移動的工作,並移動其上下游 的工作 Step 7:假如仍有resource未平衡,則回到 Step1,否則即停止 E-Business Lab, IM, NTUST

  15. CAO 的步驟 E-Business Lab, IM, NTUST

  16. CAO 的步驟 E-Business Lab, IM, NTUST

  17. Feature Description • Startup parameters: • Planned Start Time: 有PST及EPST兩種,一般採用PST,採用EPST時雖有高使用率但同時將造成高成本 • Use Alternate Resource: 決定是否採用替代資源來降低遲交的訂單數 • Utilization Fix Phase: 固定本階段之使用率及規則來平衡下個資源 • Archive Plan: 將在記憶體中儲存第一次的CAO ‧Planned Start Time - 以哪一個時間當作task的 PST ‧ EPST - Max utilization and higher WIP level ‧ PST - Max (EPST, LPST) E-Business Lab, IM, NTUST

  18. Planned Start Time • Planned Start Time • 以哪一個時間當作task的PST • EPST • Max utilization and higher WIP level • PST • Max (EPST,LPST) E-Business Lab, IM, NTUST

  19. Feature Description • Start parameters: • Coordinate Assembly: • BOM同一層的物料要不要一起延後加工 • Simulation: • 只有未排程的訂單會被移動 • No Due Date Violation: • 當不允許遲交時,如balancing moving會造成遲交,則不執行 • Respect Order Level Tolerances: • 是否要遵守tolerance 中設定的latest和earliest tolerance E-Business Lab, IM, NTUST

  20. Feature Description • Tolerances: • WIP Tolerance: • WIP等待的容忍時間,連續兩加工步驟的等待時間。 • Earliest Tolerance: • 每一個task最多只能被pull到(LPST-Earliest Tolerance)的天數 • Latest Tolerance: • 每一個task最多只能被push到(due date-Latest Tolerance)的天數 E-Business Lab, IM, NTUST

  21. Feature Description • Timing parameters: • Balancing Horizon: 計劃要balance的時間幅度 • Convergence Limit: 一個task可在balance的過程中移動的次數,超過之後就只能採取push的動作 • Balance Limit: CAO 平衡同一資源的最多次數 E-Business Lab, IM, NTUST

  22. Feature Description • Balancing Strategy用來決定訂單要怎樣來移動: • PULL_OFFLOAD_PUSH: 先往前推,若無法平衡便往替代資源堆疊,若無替代資源,則往後堆疊 • OFFLOAD_PULL_PUSH:先往替代資源堆疊,若無替代資源,則往前推,若仍無法平衡便往後堆疊 E-Business Lab, IM, NTUST

  23. Feature Description • 往替代資源的堆疊方式(offload strategy) E-Business Lab, IM, NTUST

  24. Alternative resource (替代資源) Feature Description • 往替代資源的堆疊方式(offload strategy) • consider_earlier_buckets • same_bucket_start • same_bucket_end • allow_later_endtimes E-Business Lab, IM, NTUST

  25. Feature Description • consider_earlier_buckets 選擇早一個時間區塊來推疊 E-Business Lab, IM, NTUST

  26. Feature Description • Offloading Strategies: same_bucket_start 選擇相同的時間區塊來堆疊 E-Business Lab, IM, NTUST

  27. Feature Description • Offloading Strategies: same_bucket_end 以同一個結束點為準,堆疊至同一個時間區塊以及較早的時間區塊內 E-Business Lab, IM, NTUST

  28. Feature Description • allow_later_endtimes: 允許往後面的時間區塊堆疊 E-Business Lab, IM, NTUST

  29. Feature Description Resource Criticality Rules E-Business Lab, IM, NTUST

  30. Feature Description • Resource Criticality Rules用來決定哪一個resource 優先平衡 • CRITICALITY_BASED: 最緊急的資源最優先 • 需移動的工作數(tasks)=(總超載時數) / (平均工作加工時間),需要移動的工作數越多者先選擇。 • EARLIEST_CRITICALITY: 哪一個資源最早發生產能過多情形,就優先平衡那一個資源 • POSITION_BASED: 在routing中,最早用到的資源優先平衡 • USER_DEFINED: 使用者自己定義 back E-Business Lab, IM, NTUST

  31. CRITICALITY_BASED M1 M2 M1 has a higher criticality than Resource M2 ∵M1 工作數較多 E-Business Lab, IM, NTUST

  32. Feature Description E-Business Lab, IM, NTUST

  33. How to CAO 拉到CAO介面的最下方 根據所選擇的一些Strategies,自動做產能平衡 E-Business Lab, IM, NTUST

  34. 沒有負荷過多的resource CAO 結果 • 平衡產能 解決 產能短缺 的問題 E-Business Lab, IM, NTUST

  35. 附 註 • 講義與軟體下載位置: • http://140.118.1.157 • 中文線上學習i2 Factory Planner • 下週請繳交實習課程作業! • Week2作業內容:選取一個機台做有限產能規劃,各剪取一張規劃前與規劃後的圖片貼上並說明設定哪些參數(要有圖),而獲得改善! • 因本週作業是在有Capacity shortages問題的情況下才能進行有限產能規劃 (若week1作業中Factory Problems內沒有Capacity shortages的問題,請先修改input data,讓Factory Problems中是在有Capacity shortages問題的前提下,進行有限產能規劃!) • 作業於下星期上課前mail繳交,作業需標示組別與組員學號及姓名! E-Business Lab, IM, NTUST

More Related