1 / 12

SX5, PX56, and UXC55 Day-to-day Installation Schedule

SX5, PX56, and UXC55 Day-to-day Installation Schedule. Monday 5 th September 2005. Gesco: Install CV room (PR758, 5h/day). Bouchon Closed all week from PM COSMI: Reinstall platform AM shift. COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54.

marsha
Télécharger la présentation

SX5, PX56, and UXC55 Day-to-day Installation Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SX5, PX56, and UXC55 Day-to-day Installation Schedule martin.gastal@cern.ch

  2. Monday 5th September 2005 Gesco: Install CV room (PR758, 5h/day) Bouchon Closed all week from PM COSMI: Reinstall platform AM shift COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54 martin.gastal@cern.ch

  3. Tuesday 6th September 2005 Gesco: Install CV room (PR758, 5h/day) Amec-Spie: Install ventilation electrical parts Hadrelec: Install LV cables Bouchon Closed all week COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54 martin.gastal@cern.ch

  4. Wednesday 7th September 2005 Gesco: Install CV room (PR758, 5h/day) Amec-Spie: Install ventilation electrical parts Hadrelec: Install LV cables Bouchon Closed all week COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54 martin.gastal@cern.ch

  5. Thursday 8th September 2005 (Bank Holiday?) Gesco: Install CV room (PR758, 5h/day) Amec-Spie: Install ventilation electrical parts Cegelec: Maintain PR758 Bouchon Closed all week COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54 martin.gastal@cern.ch

  6. Friday 9th September 2005 Gesco: Install CV room (PR758, 5h/day) Amec-Spie: Install ventilation electrical parts Cegelec: Maintain PR759 Bouchon Closed all week COSMI: Modify barriers on sides of PR760 rails GESCO: Install vertical ventilation ducts on RB54 martin.gastal@cern.ch

  7. Saturday 10th September 2005 Bouchon Closed martin.gastal@cern.ch

  8. Monday 12th September 2005 Gesco: Install CV room DBS: Open Plug till 9:00am Bouchon Open all week GESCO: Install remaining ducts from 9:00am on GESCO: Install vertical ventilation ducts on RB54 MADA: Install net under crane rails +Z martin.gastal@cern.ch

  9. Tuesday 13th September 2005 Gesco: Install CV room Bouchon Open all week GESCO: Install remaining ducts GESCO: Install vertical ventilation ducts on RB54 MADA: Install net under crane rails +Z martin.gastal@cern.ch

  10. Wednesday 14th September 2005 Gesco: Install CV room Bouchon Open all week GESCO: Install remaining ducts GESCO: Install vertical ventilation ducts on RB54 PH-CMI: Lower platform on overhead crane 6:00am + lower 1900kg load DBS: Close Plug PM shift martin.gastal@cern.ch

  11. Thursday 15th September 2005 Gesco: Install CV room Hadrelec: Install LV cabling Securiton: Install fire detection system Bouchon Closed GESCO: Install vertical ventilation ducts on RB54 Veritas: Control Installation of platform martin.gastal@cern.ch

  12. Friday 16th September 2005 Gesco: Install CV room Hadrelec: Install LV cabling AMEC-SPIE: Install ventilation electrical parts Bouchon Closed GESCO: Install vertical ventilation ducts on RB54 Veritas: Control Installation of platform DBS: Open Plug PM shift martin.gastal@cern.ch

More Related