1 / 24

Calais, ME-St. Stephen,NB Border Crossing Project A Case Study

Calais, ME-St. Stephen,NB Border Crossing Project A Case Study. Agenda. Introduction Planning, coordination, and permitting Considerations during Design Considerations during Construction Lessons learned. Introduction. New crossing discussed for about 30 years

overton
Télécharger la présentation

Calais, ME-St. Stephen,NB Border Crossing Project A Case Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Calais, ME-St. Stephen,NB Border Crossing Project A Case Study

  2. Agenda • Introduction • Planning, coordination, and permitting • Considerations during Design • Considerations during Construction • Lessons learned

  3. Introduction • New crossing discussed for about 30 years • 8th busiest commercial crossing along the U.S. / Canadian border • Annual traffic – 2.9 million vehicles • 7,500 AADT including 550 heavy trucks • Delays inbound to the U.S. can be up to 2 hours • Truck traffic entering Maine has doubled since NAFTA implementation (70,000 to 140,000 annually)

  4. Project Management • Maine and New Brunswick DOTs share the costs of bridge design/construction on a 50/50 basis • MaineDOT: Bridge design lead • MaineDOT: Project Manager for the bridge construction portion

  5. Agencies — U.S. • FHWA – lead federal agency • MaineDOT • GSA – cooperating agency • U.S. Department of Homeland Security • Customs and Border Protection • U.S. Border Patrol • U.S. Department of State

  6. Agencies — Canada • New Brunswick Department of Transportation • Transport Canada • Canada Border Services Agency • Canada Revenue Agency • Citizenship & Immigration Canada • Foreign Affairs Canada • Royal Canadian Mounted Police

  7. Four Alternatives including no action considered • Alternatives 2A and 3 deemed viable • Chosen: Alternative 3 Calais Industrial Park

  8. Timeline • Preliminary design and NEPA compliance – started 1999 • FHWA issued FONSI in July 2002 • Final design and permittingJuly 2002 – September 2006 • Construction Begins • NBDOT - Spring 2006 • MaineDOT – Spring 2007 • GSA and CBSA - 2007 • Open to traffic - Fall 2008

  9. This Last Year… • January 2006 – Reevaluation of 2001 Environmental Assessment • May 2006 – Army Corps of Engineers request for details • June 2006 – Maine DOT replies • June 2006 - US Coast Guard Approval • Sept 2006 – Army Corps of Engineers approval • Project tendered September 27, 2006

  10. Planning • Maine and New Brunswick circulated studies at same time • Changes in process (New Brunswick was very flexible) • Public Involvement • 9 PAC meetings, 2 public meetings, and 1 formal public hearing • MaineDOT – GSA enter into a cost reimbursement agreement for NEPA

  11. International Coordination • Partnership, respect for others’ process, flexibility • International Stakeholders workshops • Every 6 months to 1 year throughout the process • International partnering agreement • Master schedule discussed and developed • Good forum for troubleshooting problems like labor issues • Communication between workshops • Find ways to maintain national focus for future funding purposes • TBWG, BSPC, etc.

  12. Permitting — Coast Guard Bridge Permit • Required for an international bridge • Cooperating agency under NEPA • Bridge permit • 40% plans required • Approved Presidential Permit is also required • Long lead time is necessary

  13. Permitting – Presidential Permit • U.S. Department of State 2003-2005 • No precedent for the northern border • First one in at least 30 years • Guidelines for complete application • State Dept. distributes application to at least 55 agencies for comment and determinations • Prepared and circulated own EA and FONSI as part of their process as well

  14. Treaties and Approvals • Transport Canada – New Brunswick agreement • This project spurred a new Canadian equivalent of the U.S. Presidential Permit process • International Boundary Commission approval • International Joint Commission or exchange of diplomatic notes required between Foreign Affairs Canada and U.S. State Department • MaineDOT - New Brunswick agreement to construct and reimburse

  15. Design Considerations — U.S. • Inspection facility – increased in size from 20 to 50 acres. (Post 911) • MaineDOT – GSA cost reimbursement agreements • Advance notice for materials and people crossing the border • Buy America clause for steel • MaineDOT – NBDOT funding and management agreement • Bridge contractor ‘fact sheet’ and prequalification • Coordination between GSA and MaineDOT of design issues; staging issues, exchange of plans, etc.

  16. Considerations During Construction - Labor • Labor and requirements for foreign workers • Human Resources Development Canada-Canadian Labor Market Opinion • CBSA – immigration • Maine Dept of Labor • Security and background check • Ideal worker – dual citizenship, no criminal record

  17. Considerations During Construction - Security • Security during construction • U.S. Border Patrol • RCMP • Movement of workers; must be able to cross border within project limits • No precedent on this issue

  18. Considerations During Construction - Taxes

  19. Lessons Learned • Partnerships among agencies on both sides of the border that are built to last • Respect for others and stay flexible • Communicate and communicate some more • Combine NEPA/Presidential Permit Process as much as possible • Maximize the use of the cooperating agencies • Taxation issues for international bridge projects are complex

  20. Project Status International Bridge Construction (11.58 Million) • March 2007 – Summer 2008 U.S. Inspection Facility • Summer 2007 – Fall 2008 US Route 1 (9.33 Million): • April 2007 – Summer 2008 NB Route 1: • Spring 2007 Canadian Inspection Facility • Summer 2007 – Fall 2008

  21. Calais, ME-St. Stephen,NB Border Crossing Project

More Related